Force account work
Force account work, also known as work-by-force account, or time and material work, is a payment method for construction work where there is no existing agreement on cost.
In this case, the works are undertaken with the understanding that the client will pay the contractor according to the actual cost of their labour, materials, and equipment, with an additional percentage for overheads and a mark-up for profit.
It can be used when the contractor and client are unable to agree a unit price or lump sum amount, or if these methods are impracticable, for example, when the quantities and scope of work are unknown at the time of tendering, or for a change order requiring extra, unforeseen work identified after construction has already begun.
Force account work can permit the early start of construction work in critical areas, and can save staff time and overhead costs that would be required for contract package preparation, bidding, evaluation and the award of contracts.
However, it can leave both parties open to unknown costs. The client may not know the quantity, or rates of the works required, and the contractor may agree to very broad terms such as 'all costs' which can leave them struggling to make claims later in the project.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.