Target cost for construction
Target costs are generally associated with cost-reimbursable contracts. They introduce a mechanism enabling the contractor, and sometimes the consultant team, to share in the benefits of cost savings, but also to bear some of the client's cost when there are cost overruns. Contracting the contractor and the consultant team on a target cost basis can be an effective way of ensuring good collaboration.
The target cost is set early in the project, and then cost savings or overruns are shared based on an agreed formula. The aim is to provide a financial incentive encouraging cost control, rather than to penalise. Bonus and penalty payments are usually capped to prevent over-zealous or adversarial behaviour.
Target costs might be set for the overall project, or for specific elements of the works. Agreeing the target cost requires that the client has sufficient knowledge and experience to be able to accurately estimate the likely cost of the works and to negotiate effectively with the contractor and sometimes the consultant team.
Examples of target cost contracts include the New Engineering Contract (NEC) Engineering and Construction Contracts Option C: Target contract with activity schedule and Option D: Target contract with bill of quantities.
NB: According to NRM2: Detailed measurement for building works, in the context of bills of quantities, the term ‘cost target' means; '...the total expenditure for an element or
work package.'
[edit] Related articles on Designing Buildings
- Bill of quantities.
- Construction contract.
- Contract condition.
- Contract sum.
- Cost overruns.
- Cost-reimbursable contract.
- Disallowed cost.
- Fast-track construction.
- Fixed price contract.
- Force account work.
- Guaranteed maximum price.
- Lump sum contract - pros and cons.
- New Engineering Contract.
- Open-book accounting.
- Procurement route.
- Target contract.
[edit] External references
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.