Payment for extra work
Building works are complex, and it is common for a contractor to carry out works not described in the original contract documents for which they consider they are entitled to additional payment over and above the original contract sum. However, the fact that a contractor has carried out extra work does not automatically mean they have a right to payment for it.
The exact conditions under which additional payment is merited should be set out in the terms of the contract, however, generally, the contractor must be able to prove the following:
- The contract sum does not include the additional work.
- There was an express or implied promise to compensate the contractor for the work.
- The work was instructed by an authorised agent.
- Any conditions precedent to payment, as imposed by the contract, have been fulfilled.
For example, where the contractor has carried out extra work or uses superior materials to those specified, but they have not been instructed to do so, this will not entitle them to extra payment. Similarly, if the employer agrees to different work, they will not necessarily be liable for any additional payment if they were not informed of the increased costs involved.
Generally, in an emergency situation where a contractor pays a sum to preserve the employer’s property, and has not been possible to obtain instructions from the employer, the contractor will be entitled to additional payment.
If the employer refuses to provide additional payment for extra work, the contractor may refuse to carry out the work. If the employer promises the additional payment, and it later transpires that the work is included in the original contract sum and so is not ‘extra’, the promise to pay will generally not be binding.
Even if the employer has had the benefit of extra work, in the absence of written instructions, it is generally held that the contractor will be unable to recover payment.
The contractor should consider whether what they think is ‘extra work’ is provided for by the clauses of the contract.
Typically, contracts provide for changes to the works described in the contract documents through variation clauses. A variation (sometimes referred to as a variation instruction, variation order or change order) is an alteration to the scope of works in the form of an addition, substitution or omission from the original scope of works. Variations may also be deemed to occur if the contract documents do not properly describe the works actually required.
Variation instructions must be clear as to what is and is not included, and may propose the method of valuation.
For more information see: Variations.
[edit] Related articles on Designing Buildings
Featured articles and news
Listed despite problems with its design.
Zen and the art of cycling exploration.
Design Council Homes Taskforce launched
To support government 1.5 million homes target within UK climate commitments.
The story of this knowledge quarter building.
In ecology, in hydrology, in biology and in architecture.
Creating environments that promote physical, mental, and social well-being.
UK cases of neutral current diversion
Research project looks for example contributions.
Overstocking and macro-economics cause a decline.
The 2024 update of the Common Assessment Standard
Demonstrating organisational capability’ to fulfil roles under the Building Safety Act.
56 recommendations for a better built environment
Published by the CIC ahead of the King’s Speech.
SkillELECTRIC Top 8 Competitors Named
in annual search for the UK’s best student electrician.
CIOB Diversity and Inclusion technical information sheet
Step-by-step guide on implementing D and I practices.
Conservation and the Indian City. Book review.
Reversibility in conservation ethics
Learning from painting conservation.
Where It's AT Podcast launched!
New CIAT Architectural Technology Podcast goes live.