Henry Boot Construction Ltd v Alstom Combined Cycles
The case of ‘Henry Boot Construction Ltd. v Alstom Combined Cycles’ [1999] set a precedent that contractor’s rates do not become reasonable or unreasonable by the execution of variations.
The extent to which bill of quantities (BoQ) rates are applicable for valuing variations in the works, is a common cause of conflict on projects, particularly when there are substantial changes in quantities. This can be a particular issue if the rate in question is abnormally high or low due to the fact that an error has been incurred. Contractors argue that abnormally low rates compound losses, while clients point out that abnormally high rates exaggerate contractor profits.
In the case of Henry Boot Construction Ltd. v Alstom Combined Cycles, Henry Boot Construction Ltd. was employed by Alstom to undertake civil engineering works at a power station. Boot quoted a price for temporary sheet piling and this figure was included in the contract. As the works proceeded however, variation instructions affecting the sheet piling were issued.
Boot’s price was found to have been calculated incorrectly, meaning that the additional quantity required by the variation would have given them a large profit. Boot argued that the contract rates must be adhered to whereas Alstom argued that a fair valuation should be made.
At the trial, the judge emphasised the importance of the contract rates, ruling that they were ‘sacrosanct, immutable, and not subject to correction’ on the basis of one party’s dissatisfaction with them. He referred to Clause 55(2) in the relevant ICE Standard Form (6th ed.) contract which stipulated that there should be no rectification of errors, omissions or estimates, and that a mistake in a rate or price bound both parties equally.
The Court of Appeal endorsed the judge’s ruling in 2000, confirming that pricing errors do not allow the parties to adjust the rates.
The rates may however be adjusted where they are used to value variations:
- Where the works are not executed under similar conditions.
- Where the rate is rendered inapplicable by a substantial change in the quantities.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.