Hybrid construction contract
Contents |
[edit] Introduction
A contract is a promise or set of promises between two or more parties (the promisor and the promisee) which the law will enforce. In the procurement of construction, contracts are frequently standard, modified or bespoke. They can also be hybrid.
Hybrid contracts are agreements that cover those activities defined under the Housing Grants, Construction and Regeneration Act 1996. This includes construction and non-construction activities.
Section 105 of the Act defines construction activities (classified as a broad range of operations) covered with certain industry-specific exclusions. Non-construction activities are also defined in the Act, but they are only covered under a hybrid contract.
[edit] Hybrid contracts and payment
According to a 6 March 2020 London court ruling, the Act no longer requires hybrid contracts to identify specific construction and non-construction activities. The case of C Spencer Ltd (CSL) v M W High Tech Projects UK Limited (MW) exposed a lack of clarity regarding payments to the contractor (MW) and the subcontractor (CSL) during a project to construct a waste to energy power plant.
This ambiguity around construction and non-construction activities was the cause of court decisions in the past. However, the 2020 ruling stated that the phrase “only in so far as it relates to construction operations" was not necessary with regard to payment terms for non-construction activities in hybrid contracts.
This is clarified further by Simmons+Simmons:
"Hybrid construction contracts are those which include both construction operations covered by the Housing Grants, Construction and Regeneration Act 1996 (the Act) and non-construction operations. The Act has been of great assistance to the construction industry by providing clear and certain provisions in respect of payment applications and the dispute resolution procedure, which has in turn improved cash flow. However, the Act is not as comprehensive as some might have hoped. The use of ‘hybrid contracts’, i.e. those which include both construction operations (as defined by s.104 of the Act) and non-construction operations (not covered by the Act), has resulted in uncertainty.
"The dispute between M W High Tech Projects UK Limited (MW) and C Spencer Ltd (CSL) arose out of this uncertainty. In this case, the court found that payment notices for hybrid construction contracts do not need to separately identify the sums owing for ‘construction operations’, together with the basis of the breakdown, in order to be valid."
[edit] Related articles on Designing Buildings Wiki
- Act.
- Construction contract.
- Construction contract conditions
- Fair payment practices.
- Housing Grants, Construction and Regeneration Act HGRA.
- Modifying clauses in standard forms of construction contract.
- Scheme for Construction Contracts.
[edit] External resources
- England and Wales Court of Appeal (Civil Division) Decisions, C Spencer Ltd v M W High Tech Projects UK Limited [2020 EWCA Civ 331 (06 March 2020)].
- Legislation.gov.uk, Housing Grants, Construction and Regeneration Act 1996.
- Out-Law News, Court of Appeal clarifies UK Construction Act treatment of hybrid contracts, 9 March 2020.
- Simmons + Simmons, Hybrid construction contracts - payment notices.
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.