Deferment of possession
Contracts generally grant the contractor exclusive possession of the site until practical completion when a handover meeting takes place and possession reverts to the client (see handover to client). The contract may state the date for possession of the site by the contractor (sometimes called the 'commencement date'), or, if not, then the site must be handed over to the contractor within a reasonable time after signing of the contract.
Some contracts (such as the JCT Standard Form of Building Contract) will entitle the client to defer giving the contractor possession of the site for a period of up to six weeks unless a shorter period was stipulated in the contract particulars (it is probably unwise to reduce the period). This provision enables the client to defer possession without being in breach of contract.
It is considered that deferment of possession is a positive activity which the employer should signal by giving written notice although that is not expressly stated.
Deferment of possession can be considered a relevant matter, giving rise to the possibility of the contractor claiming an extension of time or loss and expense. However, for such a claim to succeed, the deferment must have a material effect on the regular progress of the works. Obviously, deferment will have an immediate effect on progress, however, it does not extend the contract period, it simply moves it in time with dates for possession and completion which continue to have the same relationship to each other.
If the contractor is given early notice of deferment, they are likely to incur far fewer costs than if the deferment is only notified a few days before start on site. Issues that might be considered include:
- Plant hire.
- The possibility of using operatives elsewhere.
- Delivery dates
- Key dates for sub-contractors
- The possibility of increased costs and interest charges.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.