Possession of the site by the contractor
Contracts generally grant the contractor exclusive possession of the site until practical completion when a handover meeting takes place and possession reverts to the client (see Handover to client).
The contract may state the date for possession of the site by the contractor (or commencement date), or, if not, then the site must be handed over to the contractor within a reasonable time after signing of the contract.
If the client fails to give possession of the site to the contractor, and there are no provisions for delay in the contract, then they will be in breach of contract. Even if the contract does provide for delay in giving possession of the site to the contractor, the contractor will still be able to claim for an extension of time and perhaps loss and expense.
A formal handover meeting when the contractor takes possession of the site is an opportunity to:
- Handover keys.
- Discuss issues related to continued occupation of any part of the site (particularly on refurbishment projects) such as access.
- Discuss security.
- Issue any significant information about the site (such as site services, tree preservation orders, etc.).
- Discuss ongoing maintenance, operation and protection issues regarding existing structures, landscape or other features to be retained.
- Discuss noise and dust reduction measures.
- Verify insurance provisions.
- Read meters.
- Provide contact details for key personnel on both sides.
- Discuss access for client's personnel and representatives or other client contractors.
See also Pre-contract meeting. The pre-contract meeting is an important meeting that takes place after the contractor has been appointed but before work commences on site. It is an opportunity to for the project team to meet (perhaps for the first time) and to plan the construction stage.
On certification of practical completion, the contractor will give possession of the site back to the client (see Handover to client).
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.