Force majeure in construction
The term ‘force majeure’ comes from French law, where it translates as 'superior force' (as opposed to ‘vis majeure’ or ‘vis major’ which refers to an act of God). Whilst in France, the term has a defined legal meaning, in English law it does not, and it is dealt with in different ways by different forms of contract.
Very broadly, it relates to exceptional, unforeseen events or circumstances that are beyond the reasonable control of a party to a contract and which prevent or impede performance of their obligations under the contract. Generally it cannot be an event that the party could reasonably have avoided or overcome, or an event attributable to the other party.
Clauses referring to force majeure attempt to set out the circumstances to which the term applies to and prescribe how such situations should be treated. Depending on the provisions of the contract, the following may be considered to constitute force majeure:
- Unforeseen changes to legislation.
- Wars and other hostilities (such as terrorism).
- Fires.
- Exceptionally adverse weather.
- Civil unrest, such as riots or revolution.
- Strikes (other than by the contractor or subcontractors).
- Natural catastrophes such as earthquakes, floods and volcanoes.
- Epidemics or pandemics.
In some contracts, force majuere is considered a 'relevant event', that may allow the contractor to claim an extension of time if they have been prevented or impeded from performing their obligations under the contract. Although, if the contractor has continued to perform their duties, despite the occurrence, they may not be able to make a claim.
As these conditions tend not to be defined, it can be difficult to determine whether they have arisen or not. For example, when does a virulent virus constitute an epidemic? This has become particularly significant in recent years due to the increasing number of exceptionally adverse weather events (in particular flooding), as well events such as foot and mouth, swine flu and restrictions on air travel due to volcanic ash clouds.
Whilst clients will generally accept the contractor cannot perform their duties under the contract where there is genuine force majeure, problems arise when the client believes the contractor is unnecessarily claiming force majeure for commercial gain and that the situation could have been foreseen, avoided or mitigated. Disputed claims are particularly common in relation to exceptionally adverse weather as the term is not always defined.
Force majeure clauses need to be flexible enough to cover events which are by their very definition are unforeseeable, but specific enough to prevent disputes arising.
Some forms of construction no longer use the phrase force majeure, but instead include clauses to deal with the specific circumstances that might arise.
In situations where a contractual obligation becomes incapable of being performed, the occurrence might be considered to be a 'frustration event' resulting in termination of the contract. Frustration occurs when circumstances that are not the fault of either party mean it is impossible to continue with the contract. The contract will come to an end without any party being considered to be in breach.
For more information, see Frustration.
NB The Chartered Institute of Procurement & Supply (CIPS) Glossary of procurement terms, defines a force majeure as: ‘Circumstances that cannot be foreseen which prevent a contract from being fulfilled.’
[edit] Related articles on Designing Buildings
- Breach of contract.
- Clear contracts during uncertain times.
- Compensation event.
- Concurrent delay.
- Consequential loss.
- Coronavirus and force majeure.
- Exculpatory clause.
- Exigency.
- Extension of time.
- Neutral event.
- Frustration.
- Liquidated damages.
- Loss and expense.
- Relevant event.
- Termination.
[edit] External references
- Matsoukis v Priestman & Co (1915).
- Lebeaupin v Crispin (1920).
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.