Consequential loss
In the event that there are problems with a development, it is possible that losses will be incurred by the injured party. For example, the cost of repairs, loss of rent, loss of profit and so on. The party that suffers the loss may then try to recover it from the party that caused it. Under the common law of negligence, losses that are purely economic (such as loss of profit) are generally not recoverable, but under contract law they may be, depending on the wording of the contract.
The general position regarding losses resulting from a breach of contract was established by the case of Hadley v Baxendale (1854) where the court held that the injured party could recover losses that could be reasonably considered to arise naturally from the breach of contract in the usual course of things (direct losses), or losses that whilst they may not arise naturally from the breach, could have been reasonably contemplated by the parties to the contract at the time that they entered into that contract (indirect or consequential losses).
Losses that are unusual, special or unlikely are generally considered too ‘remote’ to be recoverable unless the special circumstances were known at the time that the contract was entered into, whether or not they were caused by the breach. If this were not the case, an almost unlimited liability could arise for losses that were entirely unforeseeable.
This position however remains fairly open-ended and leaves a great deal of uncertainty as to whether a loss could have been ‘reasonably contemplated’ at the time that a contract was entered into. As a result, in order that both parties can understand specifically those losses that will be recoverable, it is very important that they are set out explicitly and very clearly in the contract.
Very broadly, contracts often allow direct losses to be recovered (such as the cost of repairs), but may exclude indirect or consequential losses (such as loss of profit).
However, it is not always this straight forward. For example, profit can be held by the courts to be a direct loss (British Sugar plc v NEI Power Projects Ltd and Another (1997)) or it may be considered that some component of profit is a direct loss. It cannot be assumed therefore that profit is excluded just because consequential losses are excluded.
The exact wording of the contract must be studied and requires very careful drafting. The FIDIC form of contract for example allows overheads, preliminaries, loss of productivity, interest and finance charges and claims preparation, but excludes profit, inflation or exchange rate fluctuations and lost commercial operation.
It is generally in the interest of the client that recoverable losses are unlimited, but for the contractor (or consultant) to try to restrict recoverable losses by excluding indirect or consequential losses.
This is also the case with regards liability to third parties, and so a similar situation is found within collateral warranties.
Contractors and consultants are likely to wish to restrict recoverable losses in collateral warranties to the cost of repairs. Clients on the other hand (or purchasers or tenants) may argue that contractors and consultants should be able to anticipate the consequences of a breach of contract and so should allow recovery of consequential losses. A compromise position is likely, for example the BPF form of collateral warranty allows consequential losses, but includes a requirement for the injured party to mitigate those losses and sets a cap for liability in respect of each breach.
It can be worth assessing what losses might occur before drafting a contract, and also defining clearly within the contract what constitutes a breach.
NB The Unfair Contract Terms Act can apply under certain circumstances and so any contractual provisions should be ‘reasonable’.
[edit] Related articles
- Breach of contract.
- Collateral warranties.
- Contract.
- Contract terms.
- Defects.
- Direct losses.
- Fluctuations.
- Hadley v Baxendale.
- Liquidated damages.
- Loss and expense.
- Measure of damages.
- Preliminaries.
[edit] External references
Featured articles and news
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA has launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.