Basement excavation
This article needs more work, to help develop this article, click ‘Edit this article’ above.
Contents |
[edit] Introduction
A basement is part of a building that is either partially or completely below ground level. Approved document B of the UK building regulations, Fire Safety, Volume 1 Dwellinghouses, defines a ‘basement storey’ as:
‘A storey with a floor which at some point is more than 1,200 mm below the highest level of ground adjacent to the outside walls.’
Basements can be constructed using brick or concrete block, poured concrete, pre-cast concrete, or even treated wood.
Basements generally become more expensive as the depth increases. However, in prime locations, the cost of land may justify multi-story basements or even below-ground parking garages. This is becoming increasingly common in central London where even larger ‘iceberg basements’ have provoked much controversy as they can cause significant disruption to and disturbance of neighbours.
See Basement Excavation (Restriction of Permitted Development) Bill and Planning (Subterranean Development) Bill.
Concerns about the disruption caused by the construction of basements, and the trend for 'iceberg' basements have resulted in attempts to introduce restrictions, such as the Basement Excavation (Restriction of Permitted Development) Bill and the Planning (Subterranean Development) Bill.
In August 2016, the City of Westminster introduced a new code of construction practice with an average levy of £8,000 on the construction of basements and a new ‘subterranean squad’ to help reduce the impact of basement construction works.
[edit] Excavation process
Depending on the size of the property, the amount of excavation and building work required and its complexity, the work for constructing a basement to a house will last typically for 12-20 weeks.
The first stage is for hoarding to be erected and usually for a timber shelter to be constructed in front of the house or around the opening to the excavation. An initial external opening to the basement area is created and temporary weather-proofing and supports are installed where necessary. A backhoe or excavator can then dig down, with excavated material brought to the surface and into a skip. Existing foundations may be underpinned if necessary as the excavation proceeds. Existing building services may need to be re-routed.
[edit] Types of construction
Very broadly, there are three generic types of basement construction:
[edit] Poured concrete
The external structure of the basement is poured into formwork, with reinforcing steel bars included if required. Forms are then stripped away after curing. This type of construction tends to be stronger than others and is much more resistant to water infiltration.
[edit] Block, masonry walls
This tends to be the most economical option for small-scale basement construction and often requires less time. However, concrete blocks are not suited to soil conditions that are prone to swelling as this applies lateral pressures to the basement wall which can weaken joints.
[edit] Precast panels
Precast concrete panels can be transported to the site and assembled on footings. This method is not as common but can be economical where there are multiple basements being constructed at the same time. If the joists between panels are not properly sealed then moisture can get trapped in the panels or penetrate to the interior and cause problems.
[edit] Waterproofing
BS 8102: 2009 Code of practice for protection of structures against water from the ground, provides three categories of basement waterproofing:
[edit] Tanking
A continuous waterproof barrier is applied to the inside or outside of the basement structure. The most common form is a bituminous ‘stick-on’ plastic sheet. Whilst this is relatively inexpensive, it can lose adhesion and is easily damaged during backfilling.
Alternatively, an external membrane can be painted or sprayed onto the external surface which can be covered by a drainage board to allow provide protection from the backfill.
[edit] Structurally integral protection
This is chemically-enhanced water-resistant concrete which can be used in combination with a waterproof membrane.
[edit] Drained cavity
Cavities are formed within between the internal and external wall and floor constructions to collect and drain away water entering the basement using a sump and pump. As well as the internal drain, a perimeter drain may also be included. This runs around the external perimeter of the building just below the level of the foundation, removing water from the building’s external face.
[edit] Insulation
As basements are surrounded by earth, their temperature has a tendency to remain fairly even throughout the year. There are several methods of insulating a basement, such as foam insulation, rigid insulation boards, or fibreglass batts. These allow for the retention of heat inside the basement and the prevention of condensation on walls which will eventually lead to mould growth. It is particularly important that basements are properly ventilated as they may have a vapour-impermeable construction and are unlikely to have openable windows.
Building services are likely to supply the basement from above, and drainage from the basement is likely to require pumping.
[edit] Risks
Compared with building higher, building down can involve more risks. The complexity of basement excavation increases with the depth, a higher water table, and a more congested site.
Prior to construction, good site information and soil tests are critical in terms of being able to adequately plan and forecast potential difficulties that may arise.
- Drainage difficulties and risks of flooding due to poor weather.
- Poor ground conditions and natural ground heave or settlement.
- Various obstructions, such as tunnels, existing services, mining works, archeological remains, and so on.
- Boundary issues that may prove to be contentious, most commonly the foundations of nearby properties (see party wall act and right of support).
- Loads from adjacent buildings and roads.
- Failure of waterproofing, insurance, and guarantees.
[edit] Related articles on Designing Buildings
- Basements in buildings.
- Basement Excavation (Restriction of Permitted Development) Bill.
- Basement impact assessment.
- Basement v cellar.
- Basement waterproofing.
- Compensated foundation.
- Diaphragm wall.
- Excavation.
- Party Wall Act.
- Pile wall.
- Planning (Subterranean Development) Bill.
- Right of support.
- Safe room.
- Substructure.
- Trench.
- Underground car park.
[edit] External references
- Building – Whole life costs basements
- Self-build – Basement extensions: Pros and cons
- DIY Doctor – Dig a basement
- About Home Design
Featured articles and news
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
Comments
When you are constructing a basement you should consider:
[edit] Level of water table
[edit] The cost