Backfilling
Contents |
[edit] Introduction
Backfilling is the process of reusing or replacing the soil that is removed during the excavation of foundations, ground bearing slabs or other groundworks to support and strengthen a structure. It protects foundations and forms part of the substructure of slabs, roadways, walkways and other groundwork elements.
Backfill can be made up of the same soil that was removed during excavation, or can be a mixture of imported soil, rocks and stones depending on the structural requirements. The need for backfilling will be established during ground investigations which will also be used by the engineers to formulate a design. Backfill is quantified in m3.
[edit] Backfill with excavated material
During the excavation process, excavated soil is set aside for later use. Once foundations or other concrete works are complete the previously set aside soil is used to backfill the foundation or other structural areas. Excess soil might be taken away from site or set aside for use in other parts of the project at a later stage. When excavated material is set aside for later use it should be protected from the elements. Excavated material should be stockpiled according to class or type of material.
The site parameters, soil type and design will dictate whether backfill with excavated materials is possible. For example, some sites might be so confined that stockpiling is not be a viable option.
[edit] Backfill with imported soil
The structural requirements for each project and situation will be unique and it might be necessary to use strengthened material for backfilling. The site constraints might also be a factor in the requirement to use imported soil.
[edit] Grading backfill
Backfill materials can generally be graded as:
- Coarse grained soils – gravelly and sandy soils ranging from clay to gravel.
- Fine grained soils of low to medium plasticity – inorganic clays of low to medium plasticity, inorganic silts and very fine sands of low plasticity.
- Rock – suitability depending on hardness and gradation. Hard rock might be specified for crushing.
- Shale – rock like material that breaks down under compaction.
- Marginal materials - including fine-grained soils of high plasticity and expansive clays.
- Commercial by-products - furnace slag or fly ash.
Backfill material should be homogeneous, consistent with required characteristics and free of organic matter and pockets. An engineer should visit the site to ensure that only the suitable backfill material is used.
[edit] Method for backfilling
Each project will have a unique specified method for backfilling. This will be established by the engineers of the project and described in the relevant specifications and drawings. There will be different methodologies for each element of groundworks in the project; the backfill requirements for supporting ground bearing slabs will be different to the backfill requirements for trenches.
In general, backfilling will be done in layers after the excavated areas are compacted and cleared of debris. Elements of working in confined spaces should be taken into consideration during the planning process to establish the methodology of backfilling required.
[edit] Related articles on Designing Buildings Wiki
- Building foundations.
- Confined spaces.
- Excavating plant.
- Ground improvement techniques.
- Groundworks.
- Mass haul movement.
- Over excavation.
- Ripping.
- Road construction.
- Substructure.
- Surplus excavated material.
- Temporary works.
- Trench support.
- Trial pit.
- Types of soil.
- Underground.
[edit] External references
Featured articles and news
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.