Activity schedules in construction contracts
![]() |
The term ‘activity schedule’ appears in contracts such as the NEC (New Engineering Contract) Option A contract and in a number of standard lump sum contracts. In FIDIC contracts (Fédération Internationale des Ingénieurs-Conseils), it could be interpreted as fulfilling the requirements of the schedule of payments in a lump-sum contract.
In essence, it relates to a programme where each activity is allocated a price and interim payments are made against completion of each activity. Its advantage is that it simplifies the administration of the interim payment process.
The activity schedule on these types of project is submitted together with a contract programme as part of the tender. It is important that all the activities priced add up to the tender sum and that major sub-contractors participate in the allocation of prices against their programmed activities. This may include payments for off-site goods and materials.
The simplest way to prepare an activity schedule is to draw up a bar chart (Gantt chart) which covers all the main activities required, separating each element of work that is sub-contracted. Some preliminaries, such as site offices, need a separate price bar for set up, operational use and dismantling activities. Other preliminaries such as staff and electrical consumption will be part of a constant bar.
Bars that are longer than a month then have their bar line split by defining more accurately the piece of work completed in that period. A time-defined period is acceptable in the case of preliminaries. The price allocated to each total element of work is then proportionately split to match the more defined elements.
The client’s cost consultant must ensure that the pricing of the activity schedule is not unduly front-loaded and fairly reflects normal cash-flow curves associated with building projects.
The contract conditions normally allow the contractor a short period of time after appointment to re-visit the activity schedule to expand its detail. In addition, during the course of the project, the activity schedule can be adjusted to accommodate variations, extensions of time and compensation events.
The preparation of a monthly submission for interim payment is best achieved by the contractor's project manager walking the site with the client’s representative to agree progress in respect of completed activities. Here some judgement needs to be exercised by the client’s representative as to what is ‘complete’, otherwise, strictly speaking, on a 100% basis the contractor would suffer massive cash-flow problems due to the withholding of payment.
Once the progress chart against the programme has been agreed it becomes a simple mathematical calculation of the relative prices to arrive at the valuation and its certification.
NB: Within the NEC3 Engineering and Construction Contract (ECC), The 'accepted programme' shows how the activities on the activity schedule are programmed. The accepted programme and the activity schedule need not show exactly the same activities, but there should be correlation between them, and they should be kept up to date. See accepted programme for more information.
[edit] Related articles on Designing Buildings Wiki
- Acceleration of construction works.
- Accepted programme.
- Baseline programme.
- Conditions of contract.
- Construction contract.
- Contractor's working schedule.
- Gantt chart.
- How progress is agreed in construction.
- Interim payment.
- Line of balance (LOB).
- Milestones.
- NEC Option A: Priced contract with activity schedule.
- Off-site goods and materials.
- Preliminaries.
- Procurement route.
- Programme.
- Programme consultant.
- Progress in construction.
- Resource management.
- Schedule.
- Schedule performance index (SPI).
- Short period programme.
- Tender works programme.
- Time-location chart.
- Time management of construction projects.
- Topping out.
- Window and door schedules.
[edit] External references
Featured articles and news
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.