Activity schedules in construction contracts
The term ‘activity schedule’ appears in contracts such as the NEC (New Engineering Contract) Option A contract and in a number of standard lump sum contracts. In FIDIC contracts (Fédération Internationale des Ingénieurs-Conseils), it could be interpreted as fulfilling the requirements of the schedule of payments in a lump-sum contract.
In essence, it relates to a programme where each activity is allocated a price and interim payments are made against completion of each activity. Its advantage is that it simplifies the administration of the interim payment process.
The activity schedule on these types of project is submitted together with a contract programme as part of the tender. It is important that all the activities priced add up to the tender sum and that major sub-contractors participate in the allocation of prices against their programmed activities. This may include payments for off-site goods and materials.
The simplest way to prepare an activity schedule is to draw up a bar chart (Gantt chart) which covers all the main activities required, separating each element of work that is sub-contracted. Some preliminaries, such as site offices, need a separate price bar for set up, operational use and dismantling activities. Other preliminaries such as staff and electrical consumption will be part of a constant bar.
Bars that are longer than a month then have their bar line split by defining more accurately the piece of work completed in that period. A time-defined period is acceptable in the case of preliminaries. The price allocated to each total element of work is then proportionately split to match the more defined elements.
The client’s cost consultant must ensure that the pricing of the activity schedule is not unduly front-loaded and fairly reflects normal cash-flow curves associated with building projects.
The contract conditions normally allow the contractor a short period of time after appointment to re-visit the activity schedule to expand its detail. In addition, during the course of the project, the activity schedule can be adjusted to accommodate variations, extensions of time and compensation events.
The preparation of a monthly submission for interim payment is best achieved by the contractor's project manager walking the site with the client’s representative to agree progress in respect of completed activities. Here some judgement needs to be exercised by the client’s representative as to what is ‘complete’, otherwise, strictly speaking, on a 100% basis the contractor would suffer massive cash-flow problems due to the withholding of payment.
Once the progress chart against the programme has been agreed it becomes a simple mathematical calculation of the relative prices to arrive at the valuation and its certification.
NB: Within the NEC3 Engineering and Construction Contract (ECC), The 'accepted programme' shows how the activities on the activity schedule are programmed. The accepted programme and the activity schedule need not show exactly the same activities, but there should be correlation between them, and they should be kept up to date. See accepted programme for more information.
[edit] Related articles on Designing Buildings Wiki
- Acceleration of construction works.
- Accepted programme.
- Baseline programme.
- Conditions of contract.
- Construction contract.
- Contractor's working schedule.
- Gantt chart.
- How progress is agreed in construction.
- Interim payment.
- Line of balance (LOB).
- Milestones.
- NEC Option A: Priced contract with activity schedule.
- Off-site goods and materials.
- Preliminaries.
- Procurement route.
- Programme.
- Programme consultant.
- Progress in construction.
- Resource management.
- Schedule.
- Schedule performance index (SPI).
- Short period programme.
- Tender works programme.
- Time-location chart.
- Time management of construction projects.
- Topping out.
- Window and door schedules.
[edit] External references
Featured articles and news
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Refurbishment for net zero; the BSRIA white paper
The everyday practice of tackling energy efficiency, fabric first, ventilation, air quality, and occupant wellbeing.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.
Foundations for the Future: A new model for social housing
To create a social housing pipeline, that reduces the need for continuous government funding.
Mutual Investment Models or MIMs
PPP or PFI, enhanced for public interest by the Welsh Government.
Stress Awareness Week ends but employer legal duties continue.
A call to follow the five Rs for the business and for the staff.
Key points and relevance to construction of meeting, due to reconvene.
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.
HBPT and BEAMS Jubilees. Book review.