Payment schedule
In construction, a payment schedule (or schedule of payments) is a list of dates setting out when payments will be made by one party to another under the terms of the contract between them. It can also also be linked to the completion or fulfilment of certain pre-agreed activities or stages, at which point payments must be made.
The Housing Grants, Construction and Regeneration Act 1996 was introduced with the purpose of ensuring that payments are made promptly throughout the supply chain and that disputes are resolved swiftly. Among the provisions included in the act was the right to be paid in interim, periodic or stage payments. Amendments made in 2011, established that dates for payments must be set out in the construction contract.
By including a payment schedule in the contract, setting out who needs to do what and by when, the likelihood of parties getting dates wrong (e.g. employer failing to serve a payment notice on time, or a contractor failing to serve an application for payment on the right date), can be reduced, and so disputes are less likely.
A payment schedule will usually include the following details:
- The starting date for the contract.
- The amount to be paid as an initial payment.
- The interval of other payments after the initial payment.
- The timeframe within which the project will be completed.
- The estimated total construction contract amount.
NB: In the case of Grove Developments Ltd v Balfour Beatty Regional Construction Ltd [2016] it was found that because the parties to the contract had not agreed to extend the payment schedule in the event that the works took longer to complete than expected, Balfour Beatty was not entitled to further interim payments and that the Scheme for Construction Contracts did not apply as there had been an adequate mechanism for payment.
As a result of this, contracts should set out how payments will be made if the works continue beyond the timeframe initially anticipated.
[edit] Related articles on Designing Buildings
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.