Baseline programme
A baseline programme may be prepared by a contractor at the beginning of a project. This is a detailed view of how they will divide the works into activities, the duration of those activities, and logic links to preceding and succeeding activities. This programme should be practicable and realistic, showing when the contractor intends to carry out each part of the works and identifying the resources they intend to use.
Under NEC3 contracts, the contractor’s programme is then submitted to the project manager, and if the project manager accepts it, it becomes the ‘accepted programme’ identified in the contract data.
The contractor’s programme is likely to be updated throughout the course of the works and when accepted by the project manager, that updated programme becomes the new accepted programme.
NEC4 introduces the new concept of ‘treated acceptance’, by which the project manager has a specified period of time to notify the contractor whether their programme has been accepted or not. If they fail to notify the contractor within this period, the programme is deemed to be accepted.
NB The CIOB Planning Protocol 2021 (CIOB PP21), a technical information sheet published by the Chartered Institute of Building (CIOB) in February 2021, defines a baseline programme as: ‘A programme typically prepared prior to the commencement of a project, representing a contractor’s planned intention for sequencing the works. This programme is later used as a baseline for measuring the contractor’s actual progress and performance.’
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Electrotechnical excellence, now open for entries.