Delay analysis
Contents |
[edit] Introduction
Construction projects are often subject to delays, irrespective of whether the contractor is or is not to blame. A delay claim for one day (or however number of days are involved) means the construction scheduled for that day was not completed, which could have severe financial implications and adversely affect the project's progress.
Delay analysis identifies why delays occur on a construction project and the impact they are expected to have on the overall programme. The outcome of the analysis may lead to legal action brought by one party to the contract.
[edit] Who is responsible
Delays in construction can be the contractor’s fault:
Not the contractor’s fault:
- Unusual weather conditions.
- Interruption in material supply, particularly if material is imported.
- Strikes.
- Conflicting or missing information in contract documents.
- Failure to give the contractor possession of the site.
Irrespective of who is at fault, such delays may have a critical financial impact on the project. When they occur, they represent a deviation from the planned programme of work and the contractor may be able to seek a time extension to compensate for the delay. In this case, they can submit a claim to the client outlining the cause and reasons for the delay. The client (or an agent acting on behalf of the client) must then evaluate whether the claim is justified and whether the contractor is entitled to compensation. Analysing who is at fault for the delay is a highly complex process and one which may lead to disputes.
Delay analysis can be undertaken
- Prospectively: Predicting what effect the delay will have on the project’s progress, prospective analysis can be used before and after the effect of the delay has occurred.
- Retrospectively: Retrospective techniques evaluate the effect that the delay will have on the project but they can only be applied once the works have been completed.
- Contemporaneously: During the delay.
The Delay and Disruption Protocol of The Society of Construction Law sets out six methods of delay analysis:
- Impacted As-Planned Analysis.
- Time Impact Analysis.
- Time Slice Windows Analysis.
- As-Planned versus As-Built Windows Analysis.
- Retrospective Longest Path Analysis.
- Collapsed As-Built Analysis.
For more information see: https://www.scl.org.uk/sites/default/files/SCL_Delay_Protocol_2nd_Edition_Final.pdf
[edit] Related articles on Designing Buildings Wiki
- Breach of contract
- Collateral warranty.
- Construction contract.
- Contract v tort.
- Contracts under seal v under hand.
- Disputes.
- Letter of intent.
- Privity of contract.
- Retrospective longest path analysis.
- Rights of third parties.
[edit] External references
Featured articles and news
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.