Progress of construction works
Most construction contracts will include a date by which the works described in the contract must be completed. This is either by means of a defined completion date, or a commencement date and a specified period for the works. This date may be varied during the works, for example if an extension of time is granted, or if the works are accelerated.
If no date or period is defined, a term will be implied that the contractor must complete the works in a reasonable time, that is, the time it would ordinarily take, plus an allowance for any extraordinary circumstances.
Unless the contract includes express provisions requiring that the works are carried out in a particular way, the contractor can achieve the completion date in whatever manner they choose, for example, by starting slowly and then speeding up, or by working sporadically. There is no implied term requiring that the works are carried out to a specific timetable.
However, many contracts include express terms requiring that the contractor proceeds ‘regularly and diligently’ with the works, irrespective of whether they are likely to achieve the completion date. They cannot work sporadically, or slow down if it becomes apparent that they will beat the completion date. Sub-contracts may include similar obligations, requiring sub-contractor progress to be reasonably in accordance with the progress of the main contract.
The term ‘time at large’ refers to a situation in which there is no date for completion, or where the date for completion has become invalid. The contractor is then no longer bound by the obligation to complete the works by a certain date. They may however still be bound by an obligation to proceed regularly and diligently or to complete the works within a reasonable time.
Designing Buildings Wiki includes a number of articles providing more information about construction progress and its measurement:
- Acceleration.
- Accepted programme.
- Activity schedule.
- Base date.
- Benchmarking.
- Completion date.
- Construction progress meeting.
- Construction progress report.
- Contractor's master programme.
- Critical path method.
- Design programme.
- Earned value analysis.
- Extension of time.
- Fast track construction.
- Gantt chart.
- How progress is agreed in construction.
- Information release schedules.
- Key performance indicators.
- Lead time.
- Line of balance (LOB).
- Logistics management.
- Milestones.
- Pareto analysis.
- Phased construction works.
- Precedence diagram method.
- Productivity in building design and construction.
- Productivity in construction: Creating a framework for the industry to thrive.
- Programme consultant.
- Programme float.
- Programme for building design and construction.
- Project programme.
- Regularly and diligently.
- Scheduling construction activities.
- Short period programme.
- Tender works programme.
- Time-location chart.
- Time at large.
- Time is of the essence.
- Time management of construction projects.
[edit]
Featured articles and news
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
A dynamic brand built for impact stitched into BSRIA’s building fabric.