Progress of construction works
Most construction contracts will include a date by which the works described in the contract must be completed. This is either by means of a defined completion date, or a commencement date and a specified period for the works. This date may be varied during the works, for example if an extension of time is granted, or if the works are accelerated.
If no date or period is defined, a term will be implied that the contractor must complete the works in a reasonable time, that is, the time it would ordinarily take, plus an allowance for any extraordinary circumstances.
Unless the contract includes express provisions requiring that the works are carried out in a particular way, the contractor can achieve the completion date in whatever manner they choose, for example, by starting slowly and then speeding up, or by working sporadically. There is no implied term requiring that the works are carried out to a specific timetable.
However, many contracts include express terms requiring that the contractor proceeds ‘regularly and diligently’ with the works, irrespective of whether they are likely to achieve the completion date. They cannot work sporadically, or slow down if it becomes apparent that they will beat the completion date. Sub-contracts may include similar obligations, requiring sub-contractor progress to be reasonably in accordance with the progress of the main contract.
The term ‘time at large’ refers to a situation in which there is no date for completion, or where the date for completion has become invalid. The contractor is then no longer bound by the obligation to complete the works by a certain date. They may however still be bound by an obligation to proceed regularly and diligently or to complete the works within a reasonable time.
Designing Buildings Wiki includes a number of articles providing more information about construction progress and its measurement:
- Acceleration.
- Accepted programme.
- Activity schedule.
- Base date.
- Benchmarking.
- Completion date.
- Construction progress meeting.
- Construction progress report.
- Contractor's master programme.
- Critical path method.
- Design programme.
- Earned value analysis.
- Extension of time.
- Fast track construction.
- Gantt chart.
- How progress is agreed in construction.
- Information release schedules.
- Key performance indicators.
- Lead time.
- Line of balance (LOB).
- Logistics management.
- Milestones.
- Pareto analysis.
- Phased construction works.
- Precedence diagram method.
- Productivity in building design and construction.
- Productivity in construction: Creating a framework for the industry to thrive.
- Programme consultant.
- Programme float.
- Programme for building design and construction.
- Project programme.
- Regularly and diligently.
- Scheduling construction activities.
- Short period programme.
- Tender works programme.
- Time-location chart.
- Time at large.
- Time is of the essence.
- Time management of construction projects.
[edit]
Featured articles and news
Download your free guide.
Four new types of prior approval for solar developments
Online Planning Portal application types from 5 September.
Election fails to spark construction industry revival
Contract awards and planning; post election.
Making diversity and inclusion easy for SMEs
The CIOB tool for companies with limited resources.
Sustainable Futures: Redefining Retrofit for Net Zero Living
BSRIA Briefing 2024, initial speakers announced.
Looking back at the UK's first Passivhaus leisure centre
Reflections on St Sidwell’s Point with CIAT.
A-Level results and electrical apprenticeships
Electrical Skills Index highlights areas with skills shortages.
One of the world's more unusual drive-throughs.
A quick introduction.
Hadrian's Wall Path and the national trails
The trails are heritage assets in their own right.
Articles on timely advice and hydraulic lime.
Building Designers Association of Australia
CIAT and BDAA sign Memorandum of Understanding.
Built Environment Inclusive partners issue statement committed to inclusion.
Building regulation requirements can have unintended consequences.
CIOB announces 2024/25 vice president
Sustainability champion Professor Saul Humphrey.
Accelerating towards a net-zero built environment.