Phased construction works
Construction works can be planned as a series of stages or phases, rather than as one continuous process.
This can be useful for clients where a complex sequence of events needs to be followed (such as on densely occupied or complex site), or where there are a number of distinct components to the works, particularly for clients who are seeking to maintain some level of business operation during construction and so wish to minimise disruption.
In such cases, the project works can be divided into a series of smaller projects, spaced out over a period of months or even years.
Phasing construction works can be beneficial in allowing a project to move forwards despite there being no guarantee of funding being available to complete it. Completing certain sections of work can make funding more attractive to potential lenders and investors than if the project has not begun at all. It can also enable the client to begin to generate income from the completed parts of the development.
Construction projects can be phased:
- By work category: Every part of a particular type of work is completed as part of one phase.
- By section: Dividing the project into different sections and completing them as separate projects.
- By partial completion: For example, the entire shell is built and the interior finished in separate phases.
Some of the advantages of phased construction include:
- Lower initial investment and so less initial risk.
- Construction costs can be spread over a longer time period.
- Income can be generated throughout the construction period.
- The ability to continue to occupy a site throughout the development.
- A smaller scope of works can result in a shorter construction schedule for key parts of the development.
- It can enable clients to continue to make changes based on response to the initial phases, market conditions and so on.
- Different parts of the works can be procured in the way most suited to them.
Some of the disadvantages of phased construction include:
- As different work phases will be spread out, the project overall will take longer.
- The costs overall may also be higher, as the works take longer, inflation is likely to have a greater impact, and it is not as possible to deliver economies of scale.
- The opportunity to make design changes may lead to scope creep.
- Maintaining business operations while construction is proceeding may be difficult.
- The possibility that delays in one part of the works will impact on other phases.
Particular care is required in relation to:
- Logistics on site when different sections are in the possession of different parties.
- The protection of completed sections from ongoing work.
- The provision of appropriate insurance at all times for parts of the site.
- The adoption of appropriate health and safety measures to deal with risks resulting from occupation of areas adjacent to, or only accessible through ongoing construction works.
- The provision of appropriate security measures.
- Continuity of systems such as building services.
Where all the works are procured under a single contract, phasing can be allowed for by sectional completion clauses. These allow different completion dates for different sections of the works. For more information see: Sectional completion.
Alternatively different aspects of the works may be procured under entirely separate contracts.
If phasing was not agreed during procurement, it may be permitted to a certain extent by partial possession. This allows the client to take possession of part of a building or site, even if the works are ongoing or there are defects that have not been rectified. For more information see: Partial possession.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.