Baseline schedule
Contents |
[edit] Introduction
Time management is one of the most important processes in project management. It is the discipline of planning and controlling the duration of a project. A baseline schedule is one of the main project management documents that should be created before the project starts. It sets out the project execution strategy, key project deliverables, activity planned dates and milestones.
Activities are grouped under different work breakdown structure levels. Engineering, procurement, production, testing, and so on are highlighted in baseline schedules.
[edit] Baseline schedule
A baseline schedule (also known as a schedule baseline or target schedule) is an approved copy of the project schedule that can be used to analyse project performance and report schedule variances. Baseline schedules create a road map to prepare the baseline budget, mobilisation plans, and resource allocation plans.
According to the Project Management Body of Knowledge (PMBOK) Guide, a Project Schedule represents 'the planned dates for performing activities and the planned dates for meeting milestones.'
Baselines are the frozen version of the project schedules. Before updating the project schedule for the first time, the baseline schedule is retained as a target. This means the baseline schedule is the same as the project schedule at the beginning.
As the project progresses and tasks are performed, the baseline schedule may deviate from the actual schedule. It may not reflect the current project status. Risks and unforeseen events may affect it, and some changes outside of the control of the project management team may cause delays.
Under these circumstances, remedial action should be taken and recovery plans created. It is important to emphasise that baselines should only be changed when there is a change in scope.
[edit] Baseline schedule tracking
After the approval of the baseline schedule by the stakeholders, it will be retained as a target. Schedule tracking is then carried out to analyse the differences between the planned and the actual dates. Changes in the critical path, schedule variances and delays are determined and reported in all updates.
[edit] Summary
In project time management, baseline schedules are used as references to analyse the schedule performance of the project. It is a reference document which compares the planned and the actual dates. A Schedule Performance Index (SPI) can be used to understand how far ahead or behind the project is at the point of analysis.
See also: Baseline programme.
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Contractor's master programme.
- Contractor's working schedule.
- Design programme.
- How progress is agreed in construction.
- Milestones.
- Programme for building design and construction.
- Scheduling construction activities.
- Time management of construction projects.
[edit] External resources
Featured articles and news
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
A dynamic brand built for impact stitched into BSRIA’s building fabric.