Baseline schedule
Contents |
[edit] Introduction
Time management is one of the most important processes in project management. It is the discipline of planning and controlling the duration of a project. A baseline schedule is one of the main project management documents that should be created before the project starts. It sets out the project execution strategy, key project deliverables, activity planned dates and milestones.
Activities are grouped under different work breakdown structure levels. Engineering, procurement, production, testing, and so on are highlighted in baseline schedules.
[edit] Baseline schedule
A baseline schedule (also known as a schedule baseline or target schedule) is an approved copy of the project schedule that can be used to analyse project performance and report schedule variances. Baseline schedules create a road map to prepare the baseline budget, mobilisation plans, and resource allocation plans.
According to the Project Management Body of Knowledge (PMBOK) Guide, a Project Schedule represents 'the planned dates for performing activities and the planned dates for meeting milestones.'
Baselines are the frozen version of the project schedules. Before updating the project schedule for the first time, the baseline schedule is retained as a target. This means the baseline schedule is the same as the project schedule at the beginning.
As the project progresses and tasks are performed, the baseline schedule may deviate from the actual schedule. It may not reflect the current project status. Risks and unforeseen events may affect it, and some changes outside of the control of the project management team may cause delays.
Under these circumstances, remedial action should be taken and recovery plans created. It is important to emphasise that baselines should only be changed when there is a change in scope.
[edit] Baseline schedule tracking
After the approval of the baseline schedule by the stakeholders, it will be retained as a target. Schedule tracking is then carried out to analyse the differences between the planned and the actual dates. Changes in the critical path, schedule variances and delays are determined and reported in all updates.
[edit] Summary
In project time management, baseline schedules are used as references to analyse the schedule performance of the project. It is a reference document which compares the planned and the actual dates. A Schedule Performance Index (SPI) can be used to understand how far ahead or behind the project is at the point of analysis.
See also: Baseline programme.
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Contractor's master programme.
- Contractor's working schedule.
- Design programme.
- How progress is agreed in construction.
- Milestones.
- Programme for building design and construction.
- Scheduling construction activities.
- Time management of construction projects.
[edit] External resources
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February