Extension of time EOT in construction contracts
Contents |
[edit] What is an extension of time?
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. This is described as an extension of time (EOT).
Mechanisms allowing extensions of time are not simply for the contractor's benefit. If there was no such mechanism and a delay occurred which was not the contractor’s fault, then the contractor would no longer be required to complete the works by the completion date and would only then have to complete the works in a 'reasonable' time, and the client would lose any right to liquidated damages.
[edit] How is an extension of time granted?
When it becomes reasonably apparent that there is, or that there is likely to be, a delay that could merit an extension of time, the contractor gives written notice to the contract administrator identifying the relevant event that has caused the delay. If the contract administrator accepts that the delay was caused by a relevant event, then they may grant an extension of time and the completion date is adjusted.
[edit] What types of delays might allow an extension of time?
Relevant events that might allow an extension of time may include:
- Variations instructed by the contract administrator on behalf of the client.
- Exceptionally adverse weather.
- Civil commotion or terrorism.
- Failure of the client or their consultants to provide information.
- Delay on the part of a nominated sub-contractor.
- Statutory undertaker’s work.
- A delay in giving the contractor possession of the site.
- Force majeure (such as an epidemic or an 'act of God').
- Loss from a specified peril such as flood.
- Delays in the supply of materials or goods by the client.
- Strikes.
- Changes in statutory requirements.
- Delays in receiving permissions that the contractor has taken reasonable steps to avoid.
The contractor is required to prevent or mitigate the delay and any resulting loss, even where the fault is not their own.
[edit] How are claims for extension of time assessed?
Assessing claims for an extension of time can be complicated and controversial. There may be multiple or concurrent delays, some of which are the contractor's fault and some not. There are many occasions where contractors contribute to delay themselves by their performance during design periods, when producing drawings, mock ups and samples or in interfacing with sub-contractors.
Crucial in assessing applications for extension of time is the quality of the information provided and records available. For more information, see How to prepare a claim for an extension of time.
Claims should be judged against the actual progress of the works, not the programme, and must demonstrate the link between the breach (cause) and the delay.
The contract administrator may review extensions of time after practical completion and further adjust the completion date.
Claims for extension of time can run alongside claims for loss and expense (relevant matters) however, one need not necessarily lead to the other.
It is very important when deducting liquidated damages to ensure that the correct contractual procedures are adhered to. In the case of Octoesse LLP v Trak Special Projects Ltd [2016], Justice Jefford held that Octoesse was not entitled to deduct liquidated damages as they had agreed to an extension of time after a certificate of non completion had been issued. The JCT Intermediate Building Contract is constructed such that:
'If the Contractor fails to complete the Works or a Section by the relevant Completion Date, the Architect/Contract administrator shall issue a certificate to that effect. If an extension of time is made after the issue of such certificate, the extension shall cancel that certificate and the Architect/Contract Administrator shall where necessary issue a further certificate.'
As Octoesse had not issued a further certificate of non completion, they were not entitled to deduct liquidated damages.
To find out more, see Octoesse LLP v Trak Special Projects Ltd.
[edit] Related articles on Designing Buildings
- Adverse weather during construction.
- Certificate of non completion.
- Common refusals of extensions of time.
- Completion date in construction contracts.
- Concurrent delay.
- Contract administrator for construction contracts.
- Contract claims in construction.
- Contractor delay.
- Delays on construction projects.
- Extension of time - approval letter example.
- Force majeure in construction.
- How to prepare a claim for an extension of time.
- Liquidated damages in construction contracts.
- Loss and expense.
- Octoesse LLP v Trak Special Projects Ltd.
- Practical completion.
- Reasonable objection.
- Reasonable time.
- Relevant event.
- Relevant events v relevant matters.
- Relevant matters in construction contracts.
- Time at large.
- Variations in construction contracts.
[edit] External references
- Herbert Smith, Extensions of Time: What Happens If the Contractual Machinery Breaks Down?
- Atkinson Law, Delay and Disruption - The Contractor's Obligations as to Time.
Featured articles and news
BSRIA Statutory Compliance Inspection Checklist
BG80/2025 now significantly updated to include requirements related to important changes in legislation.
Shortlist for the 2025 Roofscape Design Awards
Talent and innovation showcase announcement from the trussed rafter industry.
OpenUSD possibilities: Look before you leap
Being ready for the OpenUSD solutions set to transform architecture and design.
Global Asbestos Awareness Week 2025
Highlighting the continuing threat to trades persons.
Retrofit of Buildings, a CIOB Technical Publication
Now available in Arabic and Chinese aswell as English.
The context, schemes, standards, roles and relevance of the Building Safety Act.
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.