Completion date in construction contracts
Most construction contracts set a date by which the works described in the contract must be completed (the completion date or contract completion date). This is not the date by which all obligations under the contract have to be discharged, but the date by which 'practical completion' must be certified. That is, the date by which the works have been completed and the client can take possession of the site, albeit there may be very minor items outstanding that do not affect beneficial occupancy by the client.
Certifying practical completion (referred to as 'substantial completion' on some forms of contract) returns possession of the site to the client, releases half of the retention, ends the contractor's liability for liquidated damages and signifies the beginning of the defects liability period. The defects liability period (sometimes called the rectification period) typically lasts six to twelve months during which the client may occupy the premises and the contractor must rectify any defects that are identified.
The completion date may be altered during the course of the contract, for example if the date the contractor takes possession of the site to begin construction is delayed, or if an extension of time is granted due to delays to the works that are not the contractor’s fault. Practical completion therefore must be certified by the most recently agreed completion date.
If practical completion is not certified by the most recently agreed completion date, then the contractor may be liable to pay liquidated and ascertained damages to the client. These are pre-determined damages set at the time that the contract is entered into, based on a calculation of the actual loss that the client is likely to incur if the contractor fails to meet the completion date. Some contracts require that a certificate of non-completion is issued as a pre-requisite to deducting liquidated and ascertained damages.
Where the contract requires sectional completion of the works, then separate dates for completion and separate rates of liquidated and ascertained damages should be set for each section.
NB: There can be a cascade effect, where delays in one section cause delays in another. The contractor may then be liable to pay liquidated and ascertained damages for each section.
On construction management contracts, a separate completion date must be set for each trade contract. Once all trade contracts have been certified as practically complete, the construction manager issues a certificate or project completion. The same is true on management contracts, where each works contract must be dealt with individually.
Documentation that should be issued to the client on certification of practical completion may include:
- A draft building owner's manual.
- A building user's guide.
- The health and safety file.
- The building log book.
- A construction stage report.
Notes:
- If a contract does not specify a completion date, then the works should be completed within a reasonable time, although it is unlikely that such an ambiguous arrangement would allow the client to deduct liquidated and ascertained damages.
- Construction contracts will generally include a provision requiring that the contractor proceeds ‘regularly and diligently’ irrespective of whether it is apparent that the completion date will be achieved.
- Practical completion is not a term recognised in some recently developed contacts such as PPC 2000 and other partnering contracts which simply refer to 'completion'. See Practical completion for more information.
- The 'contractor’s planned completion date' is the date shown on the contractor’s programme as being the date when the contractor plans to complete the works under the contract. This may be different to the contract completion date.
- The 'date for completion' is the date by which the contractor is expected to complete the works, which may be earlier or later than the contract completion date.
Ref Society of Construction Law Delay and Disruption Protocol, 2nd edition, February 2017, published by the Society of Construction Law (UK). https://www.scl.org.uk/resources/delay-disruption-protocol
See also: Failure to complete construction works.
[edit] Related articles on Designing Buildings
- Building completion.
- Certificate of non completion.
- Completion.
- Concurrent delay.
- Contractor’s planned completion date.
- Date for completion.
- Defects liability period.
- Extension of time.
- Failure to complete construction works.
- Final account.
- Final certificate.
- Handover to client.
- Liquidated and ascertained damages.
- Loss and expense.
- Migration strategy.
- Octoesse LLP v Trak Special Projects Ltd
- Practical completion.
- Progress of construction works.
- Sectional completion.
- Time at large.
- Topping out.
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.