Trade contractor
On construction management contracts, a construction manager is appointed on a consultancy and management basis to provide advice to the client during the pre-construction stages and then to manage the construction of the works. The works are divided into packages which are contracted to separate contractors. These contractors are referred to as trade contractors rather than sub-contractors (as they are contracted directly by the client, rather than being sub-contracted to the construction manager). The separate appointment of trade contractors should reduce the cost of contracts, as the management element is being provided by the construction manager. It also allows the advancement of some works (such as groundworks or piling) which might begin even before design of the above-ground works is complete.
Characteristics of trade contracts include:
- Trade contractors may be appointed through a single-stage procurement process, or through a two-stage process with a pre-construction services agreement for the first stage.
- Each trade contract must have its own separate practical completion certification and so they may have different defects liability periods. Certification cannot be dependent on completion of works outside of the scope of the contract. As trade contracts may be completed at different times, the construction manager must ensure that measures are in place to protect completed work from ongoing activities.
- Trade contracts (such as the Joint Contracts Tribunal (JCT) CM/TC 2011) do not include provisions for liquidated damages, instead the trade contractor indemnifies the client's direct loss and/or expense for lateness.
- Trade contracts may allow for retention, or may include a requirement for a retention bond.
- Trade contracts should include requirements to adopt collaborative practices.
- As there is no main contractor, trade contractors should provide master programmes for their works.
- Trade contractors should be required to provide regular information in relation to key performance indicators.
- Where they carry out design, trade contractors may be required to provide as-built drawings.
Notes
- On management contracts, contractors are known as 'works contractors'.
- For a detailed description of the sequence of tasks necessary on a construction management contract, see the work plan: construction management: outline work plan.
NB A trades contractor (with an 's') is a more general term which simply refers to a contractor who undertakes a particular class of construction work, such electrical installation. See Trades contractor for more information.
[edit] Related articles on Designing Buildings
- Back-to-back provisions in construction contacts.
- Collaborative practices.
- Collateral warranties.
- Construction manager.
- Construction contract.
- Contracting.
- Contractor.
- Contractors master programme.
- Main contractor.
- Management contract.
- Operative.
- Procurement route.
- Sub-agent.
- Sub-contractor.
- Trade body.
- Types of contractor.
- Works contractor.
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.