Gateways in building design and construction projects
NB See also: Gate, Gateway cities and Gateway device.
As design and construction projects progress from inception through design and construction to completion and operation, it is crucial that the client retains control of the brief, the direction of development and costs.
Typically this is done by the introduction of key decision points, or gateways, at which the client assesses the state of development of the project and considers; whether it satisfies their strategic objectives, that it is affordable, that value is being delivered, and that risks are acceptable. They can then decide whether to progress to the next stage. If such a process is not introduced, there is a tendency for projects to gradually wander off course, with programme, budget and brief diverging.
There are a great number of different stages that gateways can be introduced, depending on the nature of the project, the practices of the client and the procurement route. A comparison of some standard stage definitions can be found in: Comparison of work stages.
Allowing the client to make decision about whether to proceed at gateways requires the preparation and submission of relevant information by the consultant team and contractors. As the project develops, this might include:
- Strategic brief.
- Preliminary business case.
- Project execution plan.
- Project brief.
- Concept design report.
- Detailed design report.
- Production information report.
- Tender report.
- Construction stage report.
- Final report.
- Assessment and lessons learned report.
It is important that appointment documents include a requirement for the project team members to prepare this information, and allocate responsibility for its co-ordination and compilation.
Consultants and contractors should not be permitted to proceed to the next stage until relevant information has been submitted and a decision made. It is important therefore that time is allowed within the project programme for the decision makers to be provided with relevant information, to assess it, discuss it and make a decision. This might involve meetings amongst senior members of the client team which might only be possible at specific dates. This decision making process should therefore be carefully planned and should not appear on a programme as a simple milestone with no sensible time allocation.
Decisions may involve expert assessment and advice from client representatives, independent client advisers, project managers, or even external bodies (such as external design reviews).
It is possible that the client will decide not to proceed, or will ask for further work to be carried out, whether this is revision of the design, or undertaking value management exercises to re-align proposals with the available budget. Value management is a team-based approach used to define the client's objectives and ensure that best value, whole-life solutions are selected to satisfy those objectives.
Decisions to proceed may be accompanied by the introduction of change control procedures, freezing certain aspects of the project. This ensures that approved aspects of the project are not changed without the express permission of the client. Changes to a project may have impacts on time, cost or quality. Broadly, the later in the development of a project that changes occur, the greater those impacts are likely to be.
Examples of the introduction of change control procedures might include:
- At the end of the concept design stage if the project is tendered at this stage (for example on a design and build project).
- At the end of the concept design stage, when the project brief might be frozen.
- During the detailed design stage when the detailed design, technical design and specification are finalised.
- During the tender stage when the tender documentation has been prepared.
- When the contractor is appointed and any further changes may qualify as variations.
See change control for more information.
With the introduction of building information modelling, the submission of material at gateways (sometimes referred to as employer's decision points) may also include data drops to ensure building information models are properly validated and controlled as they develop. Data is extracted from the evolving model and submitted to the client to ensure it reflects the level of detail that the project should have reached by that stage. The client will also check the data in terms of technical compliance, compliance with the brief, cost, and so on (the government also suggests ‘carbon’). See data drops for more information.
[edit] Gateways’ under the Building Safety Act 2022
The terminology of ‘gateways’ to describe the new regime’s stop-go stages does not appear in the legislation, the industry continues to use the term because it makes it easier to understand the overall concept. There are essentially three gateways, each policed by the relevant authority.
Gateway one is where planning permission is secured but, though unrelated to the Building Safety Act 2022 (BSA)
Gateway two is where building control approval is secured from the from the Building Safety Regulator (BSR). Some enabling works may start but construction work cannot start until approval is achieved.
Gateway three is where a completion certificate is secured from the BSR and the building cannot be occupied until then.
The BSR have powers to stop construction work requirements are not met, which includes work stopping between gateway 2 and 3 until plans are approved and likewise zero occupation is permitted until a completion certificate is issued at gateway 3. Evidence in line with the golden thread of information is key to the overall process.
[edit] OGC Gateway Review process
The OGC Gateway Review process offers a structure for publicly-funded projects, based around a series of independent peer reviews carried out at key stages to verify that projects should be allowed to progress to the next stage. These peer reviews, or 'gateway reviews' are commissioned on a confidential basis by the Senior Responsible Owner and are defined as:
- OGC gateway review 0: strategic assessment.
- OGC gateway review 1: business justification
- OGC gateway review 2: delivery strategy (or procurement strategy)
- OGC gateway review 3: investment decision
- OGC gateway review 4: readiness for service
- OGC gateway review 5: operations review & benefits realisation (or benefits evaluation)
The OGC process sets out in detail the issues that the client should consider at each gateway. See OGC for more information.
[edit] Related articles on Designing Buildings
- Change control procedure.
- Comparison of work stages
- Data drops.
- Employer's decision point (BIM)
- Employers information requirements.
- End of stage report.
- Gate.
- Gateway cities.
- Gateway device.
- Gateway points.
- Governance for Railway Investment Projects (GRIP).
- Level of detail.
- Milestones.
- OGC.
- Project lifecycle for major road projects.
- Risk management.
- Value management.
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.