Production information report for design and construction
The production information report is a work stage report produced by the consultant team for the client at the end of the production information stage (see free work plans on the Designing Buildings Wiki home page).
It is the last opportunity for the client to consider issues to do with the design of the development and the form of contract before the tender process begins. It may also be the first time that the client has seen drawings describing key components (such as door handles), assemblies and specialist items. As a result, the client may wish to issue the production information report (or parts of it) for consideration to key users (or user panels) and perhaps to their lawyer or other independent client advisers. Once the main contractor has been appointed, subsequent changes can become very expensive.
The production information report may include:
- The approximate quantities cost plan and cash flow projection.
- Packaging strategy (and costs associated with individual packages).
- An assessment of cost uncertainty and the reasons for this.
- Identification of provisional sums.
- A schedule of outstanding information (including any client contributions that will be required for the contract documents).
- A schedule of outstanding consents (such as statutory approvals or planning conditions).
- A description of proposed preliminaries and other items to bring to the client's attention.
- Proposed warranties and bonds.
- The proposed form of contract, contract conditions and any proposed changes to the contract.
- Proposed treatment of liquidated damages.
- A schedule of exclusions from the contract.
- Any insurance issues.
- Drawings and specifications describing key components, assemblies and specialist items.
- A list of any remaining components, assemblies, specialist items, samples or materials still requiring approval by client.
- An assessment of the possible use of preliminary contracts.
- An assessment of the possibility of ordering long-lead items early.
- The proposed date of possession.
- Tender procedures and the tender period.
- An assessment of the need to appoint site inspectors.
- An assessment of the need to appoint party wall surveyor(s).
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.