Production information
The Construction Project Information Committee (CPIC) defines production information as '...the information prepared by designers, which is passed to a construction team to enable a project to be constructed'.
(Ref. CPIC The importance of production information - The Construction Project Information Committee provides best practice guidance on the preparation of production information.)
Production information is incorporated into tender documentation and then the contract documents.
The quality of production information is extremely important. Unless it is prepared and co-ordinated properly, there will be disputes and delays on site, and costs will be incurred.
Responsibility for production information depends on the selected system of procurement and the chosen form of contract.
On traditional contracts (and management contracts and construction management contracts), production information may be produced by the consultant team, on behalf of the client. Some elements of production information may be produced by specialist contractors, co-ordinated by the lead designer. Any gaps in this information that require specialist input after the tender process should be clearly defined showing abutment details to adjacent work faces and how such work is integrated into the overall scheme.
On other forms of contract (such as design and build or private finance initiative projects), responsibility for preparing production information and co-ordinating information prepared by specialist contractors may lie with the main contractor.
Production information may include:
- Drawings (location drawings, component drawings and dimensioned diagrams).
- Specifications, design criteria and calculations (specification information can be included on drawings or in a separate specification, but information should not be duplicated as this can become contradictory and may cause confusion).
- Bills of quantities or schedules of work (schedules of work are 'without quantities' instructional specifications often produced by designers on smaller projects for pricing, or for items such as builders work and fixing schedules, such as sanitary fittings, doors, windows, ironmongery, light fittings, louvers, roller shutters, diffusers, grilles and manholes).
There should be a particular emphasis on equipment with long manufacturing times, such as switchgear, chiller units, lifts, escalators or bespoke cladding systems, and on front-end construction such as service diversions, demolition, setting out details, underground drainage, piling and groundworks.
Definitions and rules relating to drawn information for 'with quantities' projects are described the New Rules of Measurement. See New Rules of Measurement for more information.
Increasingly, software is used to prepare elements of production information such as computer aided design (CAD) to prepare drawings, common data environments (CDE), and proprietary systems for the preparation of specifications.
The advent of building information modelling (BIM) can allow the automatic generation of all elements of production information from a single co-ordinated model, resulting in a reduction in errors and so costs.
[edit] Related articles on Designing Buildings
- Bills of quantities.
- Building information modelling.
- Common Arrangement of Work Sections (CAWS).
- Concept drawing.
- Construction drawing.
- Construction Project Information Committee.
- Elevations.
- New Rules of Measurement.
- Post-production information.
- Prescriptive specification.
- Procurement route.
- Production information report.
- Schedules of work.
- Shop drawings.
- Specifications.
- Standard Method of Measurement (SMM7).
- Work section.
- Working drawings.
[edit] External references
Featured articles and news
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.