Snagging construction works
Contents |
[edit] Introduction
Snagging does not have an agreed meaning, and is not a contractual term. It is a slang expression widely used in the construction industry to define the process of inspection necessary to compile a list of minor defects or omissions in building works for the contractor to rectify.
[edit] Most common use of the term
Generally snagging refers to a process that takes place a fortnight or so prior to practical completion when an area is considered complete by a contractor and is offered ready for inspection.
A snagging list (occasionally referred to as a punch list) is prepared and issued by the appropriate certifying authority, typically this will be the architect, contract administrator or employer’s agent. The faults that are identified should be rectified prior to a certificate of practical completion being issued.
For more information, see Punch list.
Inspection should not take place without a proper 'builder’s clean', the removal of any protective material and the operation of full, permanent lighting. On large projects the inspection process may need to be carried out in sections as areas are progressively completed and closed off, even if this does not entail contractual sectional completion or handover to the client.
Snagging in such circumstances might begin months before overall project completion. It may also mean that some areas are physically complete but without the building services having been tested or commissioned as they are not operational. This should be noted on the snagging sheet. The closed-off areas are then subject to a rigorous locked-access regime to prevent deterioration and will require final inspection just prior to handover to the client.
The contract drawings and specifications, British Standards, and Building Regulations set a standard for the works, however common sense and experience should also be used in exercising judgment. For instance, a hand-applied finish will never match machined products, and a scratch on the back of the CEO’s office door is more serious than a similar scratch in the interior of a plant room. Two sets of eyes are better than one and it takes roughly an hour per 100 sq. m to thoroughly inspect an area while compiling a list.
It is important to ensure that meticulous dated records are kept and receipts of acknowledgement are filed. Defects can often become the subject of litigation long after completion and occupants can cause damage after handover. Sometimes photographic evidence can be a useful record, and software is now available to help identify and track defects.
[edit] Other uses of the term
Snagging can also be used to refer to other inspection and rectification processes:
- The preparation by the contract administrator of a schedule of minor (de minimis) outstanding items that remain on certification of practical completion. It should be noted that generally there is no provision in the contract for this.
- A schedule of significant (non de minimis) items appended to the certificate of practical completion. Again there is generally no provision in the contract for this, but it can be agreed by the parties to the contract if, for example, it is in the interests of the client to occupy the building even though significant outstanding items remain. There may also be circumstances, such as concern with business disruption, when a client settles for accepting a defect in return for discounting payment of the final account.
- A schedule of defects that have appeared during the defects liability period, issued by the contract administrator at the end of defects liability period. Such a schedule of defects is generally provided for by the contract.
- Inspection of sub-contractor works by the main contractor.
- Inspection by an independent surveyor acting on behalf of a purchaser.
[edit] Practical completion
Certifying practical completion is a very important milestone and has the effect of:
- Releasing half of the retention (an amount retained from payments due to the contractor to ensure that they complete the works).
- Ending the contractor's liability for liquidated damages (damages that become payable to the client in the event that there is a breach of contract by the contractor - generally by failing to complete the works by the completion date).
- Signifying the beginning of the defects liability period.
It is important to note that the defects liability period, which follows certification of practical completion, is not a chance to correct problems apparent at practical completion, it is the period during which the contractor may be recalled to rectify defects which appear. If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued.
See Practical completion for more information.
[edit] Related articles on Designing Buildings
- Backlog.
- Burn down chart.
- Commissioning.
- De minimis.
- Defects.
- Defects liability period.
- Defects list.
- Defective Premises - Liability and Measure of Damages.
- Defective Premises Act.
- Final certificate.
- Non-conformance report.
- Practical completion.
- Punch list.
- Schedule of defects.
- Site inspection.
- Work-to-complete list.
Featured articles and news
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Internally insulating a historical building
An experimental DIY approach using mineral thermal lime plaster.
Tree species selection for green infrastructure: A guide for specifiers.
The future of the Grenfell Tower site
Principles, promises, recommendations and a decision expected in February 2025.
Comments
For more information on snag lists (or punch lists) I recommend these 3 articls:
What is snag list or punch list, explained in simple words?
How to avoid a bad final punch list experience
The ultimate guide for a successful punch list experience