Punch list
A punch list (also known as a snagging list) is a document that is prepared close to the end of a construction project and issued by the appropriate certifying authority (typically, the architect, contract administrator or employer’s agent). It lists any faults that are identified or works that do not conform to the specifications, which should be rectified prior to a certificate of practical completion being issued.
Generally, snagging refers to a process that takes place a fortnight or so prior to practical completion when an area is considered complete by a contractor and is offered ready for inspection. It is a slang expression widely used in the construction industry to define the process of inspection necessary to compile a list of minor defects or omissions (snages) in building works for the contractor to rectify.
For more information, see Snagging.
This differs from a work-to-complete list which is compiled by a contractor and issued to each subcontractor and their crews at, or near, completion - a list of the remaining items and any defective work that subcontractors are required to complete before leaving the site.
For more information, see Work-to-complete list.
The process of inspection and going through a punch list is usually performed close to the end, if not right at the end, of construction so that the work as a whole can be reviewed and checked. The list of items to be completed or corrected is compiled by the contractor and submitted to the employer’s agent or designer (usually the architect or engineer). Lists tend to be organised either by room or by trade.
Following this, the work is inspected by the agent (sometimes along with the contractor, subcontractor, owner, and any other relevant stakeholders) to determine whether the items on the list have been resolved. Traditionally, the list would be worked through and a hole punched in the margin to indicate that the particular item of work had been completed, hence the term ‘punch list’. Today, digital software is capable of producing virtual punch lists with applications that can be operated via mobile devices as well as more complex web and desktop varieties.
Typical examples of punch list items include: repairing broken windows, replacing missing roof tiles, repainting chipped paintwork, filling cracks, and so on.
Once the list of items has been completed according to the specifications in the contract, or a mutually agreed resolution has been decided upon for certain items, practical completion can be certified.
Following practical completion, there is generally a defects liability period, during which the contractor may be recalled to rectify defects which appear. This is not a chance to correct snagging items apparent at practical completion, If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued.
For more information see: Practical completion.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.