Punch list
A punch list (also known as a snagging list) is a document that is prepared close to the end of a construction project and issued by the appropriate certifying authority (typically, the architect, contract administrator or employer’s agent). It lists any faults that are identified or works that do not conform to the specifications, which should be rectified prior to a certificate of practical completion being issued.
Generally, snagging refers to a process that takes place a fortnight or so prior to practical completion when an area is considered complete by a contractor and is offered ready for inspection. It is a slang expression widely used in the construction industry to define the process of inspection necessary to compile a list of minor defects or omissions (snages) in building works for the contractor to rectify.
For more information, see Snagging.
This differs from a work-to-complete list which is compiled by a contractor and issued to each subcontractor and their crews at, or near, completion - a list of the remaining items and any defective work that subcontractors are required to complete before leaving the site.
For more information, see Work-to-complete list.
The process of inspection and going through a punch list is usually performed close to the end, if not right at the end, of construction so that the work as a whole can be reviewed and checked. The list of items to be completed or corrected is compiled by the contractor and submitted to the employer’s agent or designer (usually the architect or engineer). Lists tend to be organised either by room or by trade.
Following this, the work is inspected by the agent (sometimes along with the contractor, subcontractor, owner, and any other relevant stakeholders) to determine whether the items on the list have been resolved. Traditionally, the list would be worked through and a hole punched in the margin to indicate that the particular item of work had been completed, hence the term ‘punch list’. Today, digital software is capable of producing virtual punch lists with applications that can be operated via mobile devices as well as more complex web and desktop varieties.
Typical examples of punch list items include: repairing broken windows, replacing missing roof tiles, repainting chipped paintwork, filling cracks, and so on.
Once the list of items has been completed according to the specifications in the contract, or a mutually agreed resolution has been decided upon for certain items, practical completion can be certified.
Following practical completion, there is generally a defects liability period, during which the contractor may be recalled to rectify defects which appear. This is not a chance to correct snagging items apparent at practical completion, If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued.
For more information see: Practical completion.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Global Asbestos Awareness Week 2025
Highlighting the continuing threat to trades persons.
The context, schemes, standards, roles and relevance of the Building Safety Act.
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.