Non-conformance report
A non-conformance report (NCR sometimes referred to as a non-conformity report) is a formal document used to identify, record, and address instances where work, materials, or processes do not meet the specified requirements or standards. It serves as a crucial tool for maintaining quality control and ensuring that construction projects comply with contractual, regulatory, and industry standards.
The primary purpose of an NCR is to document any deviation from the agreed standards, specifications, or contractual requirements. It ensures that non-conforming work is identified, assessed, and corrected to prevent recurrence and to maintain the overall quality of the project.
For example, NCRs might be required:
- When materials delivered to the site do not meet the required specifications or are damaged.
- If the work carried out does not meet the quality standards set out in the project specifications.
- If there are deviations from approved construction methods or procedures.
- Breaches of health and safety regulations or practices.
An NCR might include:
- A detailed explanation of the issue, including what was found to be non-compliant.
- The standards, specifications, or drawings that the work should have conformed to.
- Information about where and when the non-conformance was identified.
- The party responsible for the non-conformance.
- Suggested actions to correct the non-conformance.
- Review and approval by relevant parties, such as the project manager, quality control officer, or site engineer.
The NCR is reviewed by the appropriate authority to determine the severity and impact, and actions are proposed and implemented to rectify the non-conformance. The corrective actions are then reviewed to ensure they have been effective in resolving the issue, and the NCR is then formally closed.
NCRs are vital for maintaining high standards of quality on construction projects. They help to manage and mitigate risks associated with non-compliance and provide a record of issues that can be analysed to improve processes and prevent future non-conformances. They ensure that there is a clear record of issues and corrective actions, promoting accountability within the project team and, helping ensure the successful and compliant delivery of construction projects.
[edit] Related articles on Designing Buildings
- Backlog.
- Burn down chart.
- Commissioning.
- De minimis.
- Defects.
- Defects liability period.
- Defects list.
- Defective Premises - Liability and Measure of Damages.
- Defective Premises Act.
- Final certificate.
- Practical completion.
- Punch list.
- Schedule of defects.
- Site inspection.
- Snagging.
- Work-to-complete list.
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February