Non-conformance report
A non-conformance report (NCR sometimes referred to as a non-conformity report) is a formal document used to identify, record, and address instances where work, materials, or processes do not meet the specified requirements or standards. It serves as a crucial tool for maintaining quality control and ensuring that construction projects comply with contractual, regulatory, and industry standards.
The primary purpose of an NCR is to document any deviation from the agreed standards, specifications, or contractual requirements. It ensures that non-conforming work is identified, assessed, and corrected to prevent recurrence and to maintain the overall quality of the project.
For example, NCRs might be required:
- When materials delivered to the site do not meet the required specifications or are damaged.
- If the work carried out does not meet the quality standards set out in the project specifications.
- If there are deviations from approved construction methods or procedures.
- Breaches of health and safety regulations or practices.
An NCR might include:
- A detailed explanation of the issue, including what was found to be non-compliant.
- The standards, specifications, or drawings that the work should have conformed to.
- Information about where and when the non-conformance was identified.
- The party responsible for the non-conformance.
- Suggested actions to correct the non-conformance.
- Review and approval by relevant parties, such as the project manager, quality control officer, or site engineer.
The NCR is reviewed by the appropriate authority to determine the severity and impact, and actions are proposed and implemented to rectify the non-conformance. The corrective actions are then reviewed to ensure they have been effective in resolving the issue, and the NCR is then formally closed.
NCRs are vital for maintaining high standards of quality on construction projects. They help to manage and mitigate risks associated with non-compliance and provide a record of issues that can be analysed to improve processes and prevent future non-conformances. They ensure that there is a clear record of issues and corrective actions, promoting accountability within the project team and, helping ensure the successful and compliant delivery of construction projects.
[edit] Related articles on Designing Buildings
- Backlog.
- Burn down chart.
- Commissioning.
- De minimis.
- Defects.
- Defects liability period.
- Defects list.
- Defective Premises - Liability and Measure of Damages.
- Defective Premises Act.
- Final certificate.
- Practical completion.
- Punch list.
- Schedule of defects.
- Site inspection.
- Snagging.
- Work-to-complete list.
Featured articles and news
Quality Planning for Micro and Small to Medium Sized Enterprises
A CIOB Academy Technical Information sheet.
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.