Project monitoring
Contents |
[edit] Introduction
Project monitoring is the process or protecting the client’s interests from the risks associated with their interest in a development that is not under their direct control.
A project monitor is appointed, not to assume the responsibilities of the project manager or developer, but to act as an investigator and advisor to the client, responsible for protecting their interests in the development as it proceeds. In effect, the project monitor acts as the ‘eyes and ears’ of the client during the development process.
Project monitoring services can be carried out for a range of different client types:
- A funding institution which will acquire the project as an investment upon completion.
- A tenant or purchaser who will commit to lease or purchase the project upon completion.
- A bank or development finance company.
- Grant funders.
- Private finance initiative (PFI) funders.
The project monitor assesses the project as it progresses in a way that is both independent and impartial. They generally adopt a proactive rather than reactive approach, providing a form of ‘early warning system’ for the client, anticipating potential issues which may affect the project delivery. In this way, the project monitor can also be of value to the developer, as they can help ensure there is better-informed decision-making.
Issues that the project monitor will typically advise on include:
- Land and property acquisition.
- Statutory consents.
- Issues relating to the developer and project management systems.
- Financial appraisals.
- Construction agreements
- Costs.
- Programme.
- Design and construction quality.
Some of the advantages to the client of hiring a project monitor include:
- Enhanced risk management.
- Enhanced financial management.
- Enhanced programme management.
- Enhanced quality management.
- Greater protection of the client’s interests.
- Better-informed decision making.
[edit] Appointing a project monitor
Project monitors typically come from a background of surveying, commercial or project management. The specific competencies required depend on the nature fo the project. Specific sector knowledge can be an important quality for project monitors.
Upon receiving an initial inquiry, the project monitor should ensure they have the capability to provide the service required and advise the client accordingly if they are not fully competent in terms of the requirements of the project. Under certain circumstances, they may appoint a specialist sub-consultant to help them.
Before reaching a formal agreement on their appointment, the project monitor should have:
- An understanding of the project brief.
- A copy of the terms and conditions of any funding, purchase, tenancy, loan or other third party agreements.
- A scope of services required.
- Contractual terms of the appointment.
- The correct level of professional indemnity insurance.
It is generally advisable that project monitors are appointed based on the potential added value they can bring to the development, rather than solely on the lowest fee level.
[edit] Duties of the project monitor
The project monitor is reliant on the development team for the acquisition of the necessary information to perform their role. It is important, therefore, that the development team understand the need to cooperate and make information available, and measures should be put in place in the agreements between client and developer to ensure this is the case.
There are a number of key reports that a project monitor may produce during the course of a project.
[edit] Initial audit report
This report allows the project monitor to develop a close understanding of the project. It should fully cover the following:
- The specification.
- Design brief and constraints.
- Development appraisal.
- Cost plan.
- Design and construction programme.
- Design and construction team.
- Risks associated with the project.
[edit] Progress reports
Progress reports often coincide with key milestones, such; completion of design stages, the start of construction or the procurement of a construction contract. Progress reports will usually continue up to the completion of the development or the client’s interest in the development.
It is important that such reports are produced in time to inform any client decisions that are required, rather than simply acting as a record of what has happened.
[edit] Practical completion
The project monitor should prepare a completion report at this stage. This typically includes:
- Relevant statutory and non-statutory consents.
- Any defects schedules or lists of outstanding works.
- Financial report.
- Lessons learned.
- Recommendations.
- Handover documentation such as; health and safety file, relevant certificates,draft building owner's manual, building log book, building user's guide, testing and commissioning data and so on. For more information see: Handover construction site to the client.
[edit] Related articles on Designing Buildings Wiki
- Appointing consultants.
- Client.
- Client BIM adviser.
- Client design adviser.
- Conceiving construction plans.
- Construction project manager - morning tasks.
- Contract administrator.
- Employer's agent.
- Handover construction site to the client.
- Independent client advisers.
- Lead consultant for building design.
- Microsoft's six ways to supercharge project management
- Monte Carlo simulation.
- Project manager.
[edit] External resources
Featured articles and news
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Internally insulating a historical building
An experimental DIY approach using mineral thermal lime plaster.
Tree species selection for green infrastructure: A guide for specifiers.
The future of the Grenfell Tower site
Principles, promises, recommendations and a decision expected in February 2025.