Schedule of defects
A schedule of defects (or defects schedule) is issued by the contract administrator at the end of defects liability period. It identifies defects (aspects of the works that are not in accordance with the contract) that have become apparent during the defects liability period.
The contract administrator and the contractor then agree a reasonable period within which the contractor will rectify the defects identified on the schedule. Once the contract administrator is satisfied that the defects have been rectified, they issue a certificate of making good defects which has the effect of allowing the final certificate to be issued, releasing any remaining retention.
It is important to note that the defects liability period is not a chance to correct problems apparent at practical completion, it is a period during which the contractor may be recalled to rectify defects which appear. If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued. See the article on practical completion for more information.
NB: Under NEC contracts, at, or just after the defects date the supervisor issues a defects certificate, which either certifies that there are no patent defects, or lists any uncorrected defects. This is analogous to the schedule of defects. See Defects certificate for more information.
[edit] Related articles on Designing Buildings
- Certificate of making good defects.
- Contract administrator.
- De minimis.
- Defects.
- Defects certificate.
- Defects liability period.
- Handover to client.
- Latent defects.
- Liquidated damages.
- Migration strategy.
- Opening up works for inspection and testing.
- Patent defects.
- Practical completion.
- Protecting and storing rebar.
- Punch list.
- Remedial work.
- Retention.
- Schedule.
- Schedule of condition.
- Site inspection.
- Soft landings.
- Substantial completion.
Featured articles and news
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Internally insulating a historical building
An experimental DIY approach using mineral thermal lime plaster.
Tree species selection for green infrastructure: A guide for specifiers.
The future of the Grenfell Tower site
Principles, promises, recommendations and a decision expected in February 2025.