Final report for construction works
A final report is prepared by the contract administrator at the end at the end of the defects liability period once all defects have been rectified.
The final report should provide a summary of activities during the construction phase, describing:
- The works that have been completed.
- The variations that have been agreed.
- Claims for loss and expense or extension of time that have been agreed.
- The original contract sum.
- The final account.
- The completion date.
It is useful if both parties to the contract sign off the financial aspects of the report as representing the full and final settlement for the contract.
It can also be useful to prepare an end of contract report that provides greater detail about the performance of the contractor and is a record that can be referred to in the future in the event of public scrutiny, legal proceedings or if a judgement is being made about whether to employ the contractor again. See end of contract report for more information.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The future of the Grenfell Tower site
Principles, promises, recommendations and a decision expected in February 2025.
20 years of the Chartered Environmentalist
If not now, when?
Journeys in Industrious England
Thomas Baskerville’s expeditions in the 1600s.
Top 25 Building Safety Wiki articles of 2024
Take a look what most people have been reading about.
Life and death at Highgate Cemetery
Balancing burials and tourism.
The 25 most read articles on DB for 2024
Design portion to procurement route and all between.
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.