Lessons learned report for building design and construction
A lessons learned report (sometimes referred to as an ‘assessment and lessons learned report’ or ‘lessons identified report’) is an assessment of lessons that can be learned from a project that could be applied to other projects. This is particularly useful to clients who are regular developers and may run a continuous improvement programme, and may be a requirement of some funding organisations.
A lessons learned report may be prepared as part of a post project review, undertaken during the defects liability period. The purpose of a post project review is to look at the effectiveness and efficiency of the project delivery process. The lessons learned report focuses more specifically on how things could be done differently in the future.
It might identify:
- Mistakes that could be avoided in the future.
- Successful strategies that might be adopted in the future.
- Procedures or resources that could be improved.
It may be prepared by an in-house team, by members of the consultant team or by independent client advisers. If such services were not a requirement of original appointments then new appointments or re-appointments may be necessary.
Ideally, the requirement for a lessons learned report should be included in tender documentation so that members of the project team are contractually obliged to provide the necessary information and input to the report. They may be required to provide information as the project progresses (such as key performance indicators, which might require information from sub-contractors) or to maintain up to date lessons learned logs.
It is important to agree:
- The purpose of the report (who is it for and how they will use it).
- The scope of the study required.
- The reporting procedures and timescale for the study.
- The stakeholders that will be involved.
- The techniques that will be used.
- The information that is available.
The report might include an assessment of the project, or simply focus on the lessons that can be carried forward. Assessments may be both qualitative (based on research, interviews and workshops) and quantitative (such as key performance indicators or benchmarking assessments).
Qualitative assessments could include:
- Cost vs budget.
- Project progress relative to milestones.
- Number of complaints.
- Number of incidents / accidents.
- Number of working hours spent on different aspects of the works.
- Use of materials.
- Number of defects.
- Number of disputes.
- Amount of waste generated.
- Amount of recycling.
- The number of variations.
However, it is important that it does not simply become a time-consuming paper exercise. Nor should it be a PR exercise - an opportunity to pat each other on the back and claim every aspect of the project was successful. Only genuinely important aspects of the project should be assessed, and only viable and worthwhile lessons proposed for adoption.
The report might include:
- Executive summary.
- Background – including the wider context of other projects that the report will feed into, and details of any abnormal characteristics or events.
- Detailed assessment of different stages or aspects of the project.
- Things that can be taken forward to other projects.
- Things that can be changed on the project being assessed.
Aspects of the project that might be assessed could include:
- The quality of briefing documents.
- The effectiveness of communications.
- The performance of the various members of the project team.
- Quality issues.
- Technical issues.
- Health and safety.
- Certification.
- Variations.
- Claims and disputes.
- Collaborative practices.
For each lesson, the report might describe:
- What went wrong / right.
- Why it went wrong / right.
- Seriousness, ie is it worth avoiding / replicating in the future.
- If so, how can this be done.
[edit] Related articles on Designing Buildings
- Defects liability period.
- Digital engineering.
- Earned value analysis.
- End of contract report.
- Expanding the use of lessons learned to the global project environment.
- Extended aftercare.
- Key performance indicators.
- Initial aftercare.
- Learning.
- Maintenance.
- Medical Research Council Laboratory of Molecular Biology soft landings project.
- Performance in use.
- Post occupancy evaluation.
- Post opening project evaluation.
- Post project review.
- Soft landings.
- Soft Landings for owners.
Featured articles and news
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Internally insulating a historical building
An experimental DIY approach using mineral thermal lime plaster.
Tree species selection for green infrastructure: A guide for specifiers.
The future of the Grenfell Tower site
Principles, promises, recommendations and a decision expected in February 2025.
Comments