Initial aftercare for completed construction works
The soft landings framework is a joint initiative between BSRIA (Building Services Research and Information Association) and UBT (Usable Buildings Trust). It is an open-source framework that is intended to ‘…smooth the transition into use and to address problems that post-occupancy evaluations (POEs) show to be widespread’ (ref Useable Buildings Trust).
The government considers that soft landings sits alongside Building Information Modelling (BIM), as BIM feeds facility management systems and helps enable future alterations to completed buildings. As a result, it is thought that in parallel to the roll out of BIM, the government may mandate a Government Soft Landings (GSL) handover protocol for central government projects by 2016.
Soft landings includes provisions for initial aftercare and extended aftercare services for three years after the completed development has been handed over for occupation. A decision to require this aftercare should be made early during the development of the project so that the necessary services can be included in tender documents and appointment agreements.
The initial aftercare period is intended to deal with immediate problems, help the occupants understand the development, and help facilities managers learn to operate it. This is a period of intensive aftercare that will typically last 4 to 6 weeks, but may be longer for complex buildings such as hospitals and shorter for simple buildings such as shops. After this, the aftercare on site will reduce, although periodic reviews will continue.
A visible and accessible soft landings team, including members of the design and construction team, should be stationed on site to receive feedback, fine tune systems and ensure proper operation of the completed development. The architect will often be the main point of contact for occupants during this period, although queries most commonly relate to the operation of building services systems, and so the they will need good access to other members of the project team.
Aftercare meetings may be held with building users to explain how the building operates, answer questions and obtain feedback. The aftercare team may also disseminate information about problems that have been encountered, and progress that has been made, perhaps by issuing fortnightly newsletters.
There may be regular ‘walkabouts’ to assess operational performance and obtain data, and there will be specific meetings with facilities managers to explain systems operation in detail and obtain feedback.
This process also provides the opportunity for the project team to learn about problems that have been encountered, assess what steps might be taken to rectify them and consider how to avoid them on future projects.
The initial aftercare period will be followed by extended aftercare during years 1-3, when outstanding issues are resolved and post occupancy evaluations are fed-back for future projects. In year 1, problems are identified, training provided and systems fine-tuned, with regular reviews. In years 2 and 3, performance is reviewed, and post occupancy surveys carried out, but with reviews becoming less frequent.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- BIM and facilities management.
- BREEAM Aftercare support.
- Building information modelling.
- Building log book.
- Building owner's manual.
- Building users guide.
- Building performance metrics.
- Client commissioning.
- Defects liability period.
- Extended aftercare.
- Government construction strategy.
- Handover to client.
- Lessons learned report.
- Medical Research Council Laboratory of Molecular Biology soft landings project.
- Migration strategy.
- Occupation of completed construction site.
- PAS 1192-2:2013
- Post occupancy evaluation.
- Post project review.
- Performance in use.
- Snagging.
- Soft landings.
- Soft Landings for owners.
- Technical guide.
Featured articles and news
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.