CLASP
[edit] Introduction
CLASP (Consortium of Local Authorities Special Programme) was a prefabricated, light-gauge steel building system introduced in 1957 to help with the rebuilding that was urgently needed after the Second World War. It was originally devised by Donald Gibson, an architect with Nottinghamshire County Council, as a system to rebuild schools, and was further developed in association with Hertfordshire County Council and its county architect Charles Aslin.
Combining the resources of local authorities and the standardisation of components that the system involved resulted in significant cost savings. CLASP became popular in the coal-mining counties of Nottinghamshire and Derbyshire, mainly because of its ability to quickly reinstate buildings which had been badly affected by mining subsidence. British Rail (Southern Region) adopted the system in the 1960s and 70s, using it for signal boxes and station buildings.
[edit] Characteristics
CLASP’s lightweight steel components could be assembled to create a four-storey building that could be clad with a variety of modular panels, allowing a varied aesthetic. One of the system’s main benefits was that due to its cold-rolled steel pin-jointed and vibrating roller base, it could accommodate movement from subsidence, which was especially important in mining areas. Although intended originally for schools, the system was also used to build offices and housing.
Nottinghamshire has around 730 CLASP buildings, Derbyshire has 249, Durham county has 147 and Gateshead area has 135. Other areas in the UK have fewer, but still in significant numbers.
Created initially to have a design life of 60 years, many of the buildings have reached the end of their life. One of the problems associated with CLASP is the large amount of asbestos used in the construction; some of the schools still have the material in place.
CLASP fell out of favour from the late 1970s, largely because of the demise of system build generally. But it is still in use today under the name of SCOLA (Second Consortium of Local Authorities) and MACE (Metropolitan Architectural Consortium for Education). It also goes under the name of Scape System Build, a local authority-controlled company wholly owned by Derby City, Derbyshire County, Gateshead, Nottingham City, Nottinghamshire County and Warwickshire County Councils in equal shares.
A number of high-profile projects were completed using CLASP. Perhaps the most famous is Smithdon High School in Hunstanton, the first building to which the term ‘brutalist’ was applied, designed by Peter and Allison Smithson (1954); and St Paul’s School, London by Powell & Moya (1968).
It is a moot point whether the results of CLASP were aesthetically satisfying: some found the buildings attractive, others found them too industrial. Detractors of CLASP called it the ‘Collection of Loosely Assembled Steel Parts’.
[edit] Related articles on Designing Buildings Wiki
- Architectural styles.
- British post-war mass housing.
- Brutalist.
- Brutalist London Map - review.
- Cite Radieuse.
- Concrete.
- Constructivist architecture.
- Deconstructivism.
- Erno Goldfinger.
- High-tech architecture.
- Howell Killick Partridge and Amis.
- Megastructure.
- Metabolism.
- Owen Hatherley - Landscapes of Communism.
- Prefabrication.
- Space, Hope and Brutalism.
- Trellick Tower.
Featured articles and news
Awe-inspiring medieval great barns.
Registered building inspectors
Building types and conflicts of interest updates explaineed.
Engineering services still struggle with labour shortages
According to latest quarterly services survey of the sector.
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.