Drywall construction
Contents |
[edit] Introduction
Drywall, also known as dry lining and plasterboard, is a material typically used for constructing walls and ceilings, as an alternative to plaster. It is made primarily from gypsum, which is a mined mineral.
Drywall can be preferable to plaster which has a long drying time, and walls and ceilings that may take weeks to plaster can be completed in days using drywall. It also has good fire-resistant characteristics, is easy to install, is durable and is relatively easy to maintain.
[edit] Production process
Drywall was invented by the US Gypsum Company in 1916 and first marketed as small fireproof tiles. Prior to this, interiors had relied on lath and plaster techniques which were time-consuming and labour-intensive. After several years, it began to be manufactured in the form of a single layer of gypsum compressed between two sheets of heavy paper. During the post-WW2 construction boom, drywall became the most common wall-covering material.
Mined gypsum is mixed with several additives, such as starch, paper pulp, and an emulsifier that acts as a thickening agent. It is blended with water to create a thick paste which is spread onto Manila paper in thick layers. Another sheet of Manila paper is placed on top before being oven-heated to dry the material out. It is then cut into sheets.
Although it differs around the world, most drywall in Europe is cut into sheets that are 120 cm wide, with 90 cm and 60 cm wide sheets also available. The most commonly cut length is 240 cm, although lengths of 250 cm, 260 cm, 270 cm, 280 cm, 300 cm, and longer are also cut. Drywall tends to be available at thicknesses of 9.5 - 25 mm.
The most common edge treatments that are available are; tapered edge, plain edge and bevelled on all sides.
A number of specialised forms of drywall can be manufactured, such as:
- Fire-rated: Fibre strands are added to the standard mixture to give a longer fire rating.
- Impact resistant: Fibre strands are added and thicker paper used.
- Moisture resistant: Water-resistant green paper can be used when the drywall is to be installed in areas prone to moisture.
- Sound board: Polymers are added which convert noise energy to heat energy.
- Lead-lined: A thin layer of lead is added between the gypsum core and the paper backing for use in X-ray rooms or areas prone to radiation.
- Flexible drywall: Where drywall is to be used for tight arches and/or curves, thinner boards are used that are ‘wetted down’ before being used.
- Blue board: A special green coating is used to cover the drywall, making it easier for veneer plastic to adhere to it.
[edit] Installation
The first step in the installation of drywall is to cut the sheets to the lengths required. This should be done on a dry and level surface using a drywall saw. A keyhole saw and/or circle cutter can be used to cut the necessary holes for electrical outlets, light switches, and so on.
Drywall panels are then fastened directly to wall studs or to furring strips that are applied over masonry surfaces. Panels are fixed to metal studs vertically, but best fixed to timber studs horizontally since timber is more likely to warp over time, and horizontally hanging (along with a drywall adhesive) helps minimise deflection. Fixing techniques include wallboard nails or plasterboard screws. Typically, screws are placed about every 10 cm.
The finishing process involves concealing the joints between panels using wallboard joint tape and a joint compound spread along each seam using a finishing knife. Once the compound has set and dried, it should be lightly sanded using sandpaper until no tape is visible on the surface and it is smooth and flush with the rest of the wall.
Drywall ceiling installation requires thinner sheets than walls, as they are not as heavy which makes them easier to install. When installing, the walls should be built first to give extra support for the ceiling.
To repair damage, joint compound is used to fill small holes that are then sanded smooth and flush. Larger holes may require filling with a piece of cut drywall and joint compound.
[edit] Related articles on Designing Buildings
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Preparing for the future: how specifiers can lead the way
Effective specificationand the Future Homes Standard.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.