Micropiles
Foundations provide support for structures, transferring their load to layers of soil or rock that have sufficient bearing capacity and suitable settlement characteristics. Very broadly, foundations can be categorised as shallow foundations or deep foundations.
Pile foundations are deep foundations. They are formed by long, slender, columnar elements typically made from steel or reinforced concrete or sometimes timber. A foundation is described as piled when its depth is more than three times its breadth.
Micropiles are piles that have a relatively small diameter, typically in the range of 100-250 mm. They can also be described as:
- Minipiles (generally mini piles are smaller than micro piles)
- Pin piles.
- Needle piles.
- Root piles.
- Lightweight piles.
The size of the pile is determined by the load-bearing capacity of the ground and the size of rig that is able to access the piling location.
They can be driven or screw piles and tend to be used where access is restricted, for example underpinning structures affected by settlement. They were first used in Italy in the 1950s in response to the demand for innovative underpinning techniques that could be used for historic buildings and monuments.
They are particularly suited to:
- Shallow bedrock.
- Boulders and cavities.
- Immediate hard strata.
- Where underpinning is required, such as for foundations adjacent to planned excavations.
Micropiles can also be used in combination with other ground modification techniques where complex site conditions and design specifications are present.
In a typical installation process a high-strength steel casing is drilled down to the design depth. A reinforcing bar is inserted and high-strength cement grout pumped into the casing. The casing may extend along the full length of the pile, or it may only extend along part of the length of the pile, with the reinforcing bar extending along the full length.
Drilling may be achieved by a removable bit, or by a sacrificial head to the steel casing.
In some cases, the steel casing may be removed, or partially removed, and further grout pumped in at pressure.
They can be installed in restricted access sites where there is low headroom by the use of lagging. This is where wood, steel or precast concrete panels are inserted behind the pile as the excavation proceeds so as to resist the load of the retained soil and transfer it to the pile. Greater capacity can be achieved by post-grouting within the bond length to increase frictional forces with surrounding soils.
There are advantages of micropiles include:
- They are small and relatively light.
- They are relatively inexpensive.
- They can be installed through almost any ground condition, making them suitable for installation in environmentally-challenging conditions, such as for wind turbine towers.
- The limited vibration and noise causes little disturbance.
- Piling rigs can be low-emission or even electrically driven.
- They can be installed while avoiding existing utilities, meaning that expensive utility re-routing is not required.
- They can be installed close to existing walls with limited headroom and congested site conditions.
- They have a high load capacity and an ability to resist compressive, tensile and lateral loads.
[edit] Related articles on Designing Buildings
- Bored piles.
- Caisson.
- Cofferdam.
- Continuous flight auger piles.
- Driven piles.
- Footings.
- Foundations.
- Geothermal pile foundations.
- Ground anchor.
- Groundworks.
- Grouting in civil engineering.
- Pad foundation.
- Pile cap.
- Pile foundations.
- Raft foundation.
- Retaining walls.
- Screw piles.
- Sheet piles.
- Types of pile foundation.
- Underpinning.
- Vibro-compaction.
- Vibro-replacement.
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.