Floor level (FL)
Contents |
[edit] Floor Level
Floor level is a general, informal term to describe the Finished Floor Level (FFL) of a building, but as it is an informal term it may refer to a bare unfinished floor level also.
[edit] Finished Floor Level (FFL)
Finished floor level (FFL) refers to the uppermost surface of a floor once construction has been completed but before any finishes have been applied. So, in concrete construction it may be the uppermost surface of a screeded finish, or in timber construction, FFL will denote the top level of floorboards, chipboard or ply decking.
Finished floor level does not take into account any applied finishes as these may be added by owners, occupiers or tenants, will vary in thickness, e.g a thick shag-pile carpet has different thickness to a laminated floor, and may be replaced.
[edit] Structural Floor Level (SFL) / Structural Slab Level (SSL)
Structural Floor Level (SFL) or sometimes Structural Slab Level (SSL) in the case of concrete frame buildings, describes the floor level prior to the addition of finishing items such as screed, underlay and flooring. The numerical measure will normally be written next to the abbreviation on a drawing often with a + to indicate vertical increase or - in the case of basements. The figure will be a certain amount above or below whatever the agreed setting out position or datum is. For example the setting out position might be 0.00, the SSL +3.0 and the FFL +3.3.
[edit] Building Ground Level (BGL)
Building Ground Level (BGL) might be used to describe the setting out position for the building ie the 0.00 from which all other levels will be measured. The height of this in relationship to the site itself will depend on the approach taken and agreed by the project team, though it will normally be slightly higher than the Ordinace Survey (OS) Level or Natural Ground Level (NGL) to allow for structural foundations.
[edit] Ordinance Survey (OS) level
Ordinance Survey (OS) level, is based on the accepted levels or measures of the lay of land across the United Kingdom, these are calculated through the use of Ordnance Survey Bench marks (BMs) which are survey marks that are made by Ordnance Survey to record the height of the landscape above Ordnance Datum. Based on these and the process of surveying, the more localised OS or what might be call Natural Ground Levels are calculated and recorded.
[edit] Natural Ground Level ( NGL)
Natural Ground Level ( NGL) is the accepted datum for a site prior to any excavation works to lay the foundations of the building.
[edit] Related articles on Designing Buildings
Featured articles and news
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.