Ordnance Datum
The term ‘Ordnance Datum’ refers to the height of mean sea-level, taken from a reference point at Newlyn in Cornwall. This is basis of the national height system for Britain.
The Newlyn Ordnance Datum was preceded by a Liverpool levelling, started in 1840 using a bench mark on St John's Church. In 1844 the datum was changed to the tidal pole in Victoria Dock, but from 1921, this has been generally superseded by the Newlyn Ordnance Datum.
In some remote islands such as Shetland and the Hebrides, datums are based on a local determination of mean sea level.
Ref https://www.ordnancesurvey.co.uk/gps/legacy-control-information/liverpool-to-newlyn
The term Above Ordnance Datum (AOD) refers to a height above the Ordnance Datum. Measurements are given a + or a – sign to signify which side of Ordnance Datum it falls.
[edit] Related articles on Designing Buildings
Featured articles and news
Art of Building CIOB photographic competition public vote
The last week to vote for a winner until 10 January 2025.
The future of the Grenfell Tower site
Principles, promises, recommendations and a decision expected in February 2025.
20 years of the Chartered Environmentalist
If not now, when?
Journeys in Industrious England
Thomas Baskerville’s expeditions in the 1600s.
Top 25 Building Safety Wiki articles of 2024
Take a look what most people have been reading about.
Life and death at Highgate Cemetery
Balancing burials and tourism.
The 25 most read articles on DB for 2024
Design portion to procurement route and all between.
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.