What notifications do you need to give when construction works are complete
Contents |
[edit] Introduction
Construction works can be complex, affecting a large number of people, and having significant health and safety and other implications. As a result, a number of approvals may be required before construction works begin, notices may have to be given of certain activities as construction proceeds, and further notices may have to be given when the works are complete.
Generally, the number of approvals and notices required will increase with the size, complexity and sensitivity of the proposed works.
Completion of the works is generally signified by certification of ‘practical completion’. It is referred to as practical completion rather than simply 'completion' as there may still be defects that emerge that require the contractor to carry out additional works, and so, even though the client may occupy the building, the contract has not been completed. However, there is no absolute definition of practical completion, and case law is very complex. See practical completion for more information.
More practically, the purpose of many notices is to ensure that requirements have been met before the building is occupied, and so completion may be signified by the works being ready to occupy.
[edit] Planning permission.
Planning permission is the granting of permission to proceed with a proposed development. Responsibility for granting permission generally lies with local planning authorities (usually the planning department of the district or borough council).
Applicants are required to inform the local planning authority when construction works are complete, and in some circumstances the permission may include planning conditions or planning obligations that must be satisfied or discharged before the development is occupied.
No completion certificate is issued by the planning authority.
[edit] Building regulations
Construction works may also need building regulations approval. The building regulations set out requirements for specific aspects of building design and construction. Building regulations approvals can be sought either from the building control department of the local authority or from an approved inspector. Generally on larger, new-build projects, a 'full plans' application will be made, meaning that full details of the proposed building works are submitted for approval before the works begin. On small projects, approval may be sought by giving a 'building notice'. In this case, a building inspector will approve the works as they are carried out by a process of inspection.
A separate notice will generally be required by the building control body, telling them when construction works have been completed.
In addition, within 5 days of the completion of the construction, a report must be issued to the building control body setting out the Target Emission Rate (TER), and Building Emission Rate (BER) or Dwelling Emission Rate (DER) of the completed building, along with any changes that have been made to the specification, and an energy performance certificate (EPC). This require that an air-permeability test is carried out to ensure the building envelope has been constructed to a suitably high level of workmanship so that air (and with it, heat) will not ‘leak’ through the building fabric.
For more information see: Target Emission Rate.
In addition, the building control body is likely to require a commissioning notice confirming that:
- A commissioning plan has been followed so that every system has been inspected and commissioned in an appropriate sequence and to a reasonable standard.
- The results of tests confirm that the performance is reasonably in accordance with the actual building design, including written explanations where there are differences.
For more information see: Notice of commissioning.
A completion certificate will be issued by the building control body (or a 'final certificate' if the building control body is an approved inspector), providing formal evidence that the building works have been approved and that, in so far as it is reasonable to determine, the works have been carried out in accordance with the building regulations
Where minor works are carried out to a property, a certificate may be issued by a trades person under the competent persons schemes.
For more information see: Building regulations completion certificate.
[edit] Health and Safety
The Construction (Design and Management) Regulations (CDM Regulations) ensure that health and safety issues are properly considered during a project’s development so that the risk of harm to those who have to build, use and maintain structures is reduced.
No notice of completion is required, however, the regulations do require that the Health and Safety Executive (HSE) is notified if construction work is likely to last longer than 30 working days and have more than 20 workers working simultaneously at any point, or exceed 500 person days. Whilst it does not include a completion date, the F10 - Notification of construction project, includes a start date and planned duration.
Note, CDM requirements may be re-triggered after this by works undertaken to rectify defects.
[edit] Other notices
Other notices might be required in relation to:
- Advertisement consent.
- Felling or lopping a tree.
- Hazardous substances.
- Listed buildings or scheduled monuments.
- Designated areas.
- Mining or working of minerals.
- Highway works.
- Works affecting a railway.
- River works.
- Works that could; pollute the air, water or land, increase flood risk or adversely affect land drainage.
- Nuclear works.
- The Licensing Act or Gambling Act.
It can also be wise to inform other interested bodies, particularly on large projects:
- Emergency services.
- Utility providers.
- Post office.
- Neighbours.
- Insurers.
- Landlords or tenants.
- Funders.
- Telecom provider.
- Facilities managers and operational services providers.
- Waste handlers.
A range of documentation may need to be issued to the client:
- The health and safety file.
- The draft building owner's manual.
- The building log book.
- A building user's guide.
- Up to date testing and commissioning data.
- Certificates and warranties.
- As-built drawings or an as-constructed building information model.
- Copies of statutory approvals, waivers, consents and conditions.
- Licences.
See Handover to client for more information.
[edit] Related articles on Designing Buildings Wiki
- Building regulations.
- Building regulations completion certificate.
- CDM.
- Community infrastructure levy commencement notice.
- Designated area.
- Environmental legislation.
- Handover to client.
- How long does planning permission last.
- Licensing.
- Listed buildings.
- Notice of commissioning.
- Penfold Review
- Planning permission.
- Statutory authorities.
- Statutory obligations.
- Statutory undertakers.
- Target emission rate.
- What approvals are needed before construction begins.
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.