Statutory undertakers
Contents |
[edit] Introduction
Statutory undertakers are bodies that have been given statutory powers in relation to functions that are of a ‘public’ character. Statutory undertakers may have rights (such as the right to carry out certain works without obtaining the normal permissions) and obligations (such as the supply of utilities).
Statutory undertakers include public bodies such as the Post Office, Civil Aviation Authority, the Environment Agency and so on, and private bodies such as those performing functions in relation to railways, canals, electricity supply, gas, water, sewerage and electronic communications.
[edit] Right to connection
It is important in the early stages of a project to assess the availability of, and rights to key services on a proposed site.
[edit] Sewers
In October 2012, Schedule 3 of the Flood and Water Management Act 2010 came into force. This requires the inclusion of sustainable drainage of surface water (SUDS) in developments that require planning approval or have drainage implications. It removes the automatic right established by the Water Industry Act to connect to public sewers and instead gives powers to local authorities as SUDS Approving Bodies (SAB’s) to approve new drainage systems and their connection to public sewers.
The costs of connection are the responsibility of the land owner. If there is no suitable main available, one may be requisitioned, but a cost is likely to be incurred for this.
[edit] Water supply
For domestic premises, the statutory undertaker (now referred to as the incumbent water company) must supply a connection to the boundary of the street (within a reasonable agreed time), but onward supply is the responsibility of the owner, and if this requires passing through others land, this may mean agreeing an easement or licence with third party land owners. If the street supply is not within a reasonable distance, the owner can require the undertaker to extend their mains, but this may incur a payment.
For non-domestic premises it is for the owner and the undertaker to reach an agreement, but if such an agreement cannot be reached, then the Director General of Water Services will make a determination.
For more information, see Incumbent water company v undertaker.
NB Water Bill, Glossary: water terms, published by the Department for Environment, Food and Rural Affairs in November 2013, describes an English undertaker as: ‘An undertaker whose appointment area is wholly or mainly in England. Undertakers are generally appointed on river basin catchments rather than political boundaries. Severn Trent is the only English undertaker whose appointment area extends into Wales. This means they have some Welsh customers, e.g. in Powys.’
[edit] Gas
Owners or occupiers have the right to receive a gas supply within a reasonable, notified time if the premises are within 23 metres of an existing mains. Otherwise, they may be connected by a pipe that they have laid themselves.
[edit] Electricity
Owners or occupiers have the right to receive an electricity supply within a reasonable, notified time, to an agreed maximum power. However the owners or occupiers may be required to pay any reasonable expenses incurred.
[edit] Electronic communications
Following the privatisation of British Telecommunications (BT), the terms for the provision of electronic communications are dependent on individual operators licences, statutory regulations and the term of the supply contract with the owners or occupiers. BT has however been designated as the provider of universal service in the UK, and under The Universal Service Obligation (USO) BT has obligations in relation to the provision of access to the telephone network, schemes for consumers with special social needs and public call box services. BT also has obligations in relation to data provision under the Enterprise Act.
[edit] Related articles on Designing Buildings
- Article 4 direction.
- Flood and Water Management Act.
- Incumbent water company v undertaker.
- Statutory authorities.
- Statutory obligations.
- Street works.
- Sustainable Urban Drainage Systems.
- Third party dependencies.
- Utilities.
- Water undertaker.
- Welsh undertaker.
- What approvals are needed before construction begins.
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Comments
We are major suppliers to Gas, Water, Comms & Electric however serving through Section 50s, is it possible to become a Statutory Undertaker so we can serve permits through Street Manager an obtain an OD batch file? Any help appreciated.