Concept design
Contents |
[edit] What is concept design?
In the construction industry, concept design represents the design team's initial response to the client's requirements. Concept design generally takes place after feasibility studies and options appraisals have been carried out and a project brief has been prepared.
Concept design is generally considered to be the first true design stage. Options appraisals and feasibility studies may include the preparation of diagrams - for example exploring the relationships between functions - but these are for analytical purposes only and are not genuine design studies.
Some designers will differentiate between 'concept design' and 'scheme design'. In this case, the 'concept' is the initial design idea, whereas the 'scheme' develops the concept, taking on board more functional and practical considerations. Most project plans have now combined these two steps into the single stage 'concept design', or 'concept'.
Concept design is followed by 'detailed design' or 'developed design' during which all the main components of the building and how they fit together are developed and described.
[edit] What does concept design involve?
During the concept design stage, the consultant team will develop:
- The design concept.
- Outline specifications.
- Schedules of accommodation.
- A strategy for obtaining planning permission and building regulations approval.
- The cost plan.
- Procurement options.
- Programme and phasing strategy.
- Buildability and construction logistics.
- Development of the project brief.
On some projects, it may also include making an outline planning application or a detailed planning application.
For more information see: Traditional contract: concept design.
The make up of the consultant team will vary depending on the type, complexity and size of the project, but on most projects of moderate complexity, it will involve an architect, building services engineer, structural engineer and cost consultant. For more information see: Consultant team.
[edit] Concept design wth building information modelling
Where building information modelling (BIM) is being used during the concept design stage, the built asset might be represented by massing diagrams or 2D symbols representing generic elements, with some critical elements developed in more detail. The project information model may also include drawings, reports and other structured information directly related to the built asset and its facilities, floors, spaces, zones, systems and components.
BIM can also be useful at this stage to generate presentation material such as photo visualisations and 3D walk-throughs that help facilitate employer assessments and consultations with user panels, champions, and other stakeholders.
[edit] What happens at the end of concept design?
At the end of the stage, the consultant team will prepare a concept design report for the client which records the basic design concepts for the preferred option that might be worth further investigation in the detailed design stage. The concept design report will also identify any instructions required from the client to steer the general direction of the project.
The project brief will continue to develop as the concept design is prepared, but it is then frozen at the end of the concept design stage and change control procedures are introduced so that only changes agreed by the client can be introduced.
An application for planning permission might also be made during the concept design stage. This is likely to be an outline planning application if made at the beginning of the stage or a detailed planning application if made once the concept design is complete.
[edit] Find out more about the tasks carried out during concept design
Detailed descriptions of the design tasks that are performed during this stage can be found at:
- Traditional contract: concept design.
- Concept architectural design.
- Concept architectural design checklist
- Concept structural design.
- Concept services design.
[edit] Related articles on Designing Buildings
- Brainstorm.
- Briefing documents.
- Concept design report.
- Concept architectural design.
- Concept architectural design checklist.
- Concept structural design.
- Concept services design.
- Design.
- Design methodology.
- Design studies.
- Detailed design.
- Feasibility studies.
- Mood board.
- Options appraisal.
[edit] External references
Featured articles and news
OpenUSD possibilities: Look before you leap
Being ready for the OpenUSD solutions set to transform architecture and design.
Global Asbestos Awareness Week 2025
Highlighting the continuing threat to trades persons.
Retrofit of Buildings, a CIOB Technical Publication
Now available in Arabic and Chinese aswell as English.
The context, schemes, standards, roles and relevance of the Building Safety Act.
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
This is exactly what i was searching for. Many people don't know how to convey what a concept design is. This article was very beneficial and i am sure it will help many budding architects to learn what a concept design in architecture actually means.