Single-stage tender
A tender is a submission made by a prospective supplier in response to an invitation to tender. It makes an offer for the supply of goods or services.
Tender procedures will vary depending on the nature of the goods or services that are being procured, but very broadly they can be classified as either single-stage or two-stage.
Single-stage tendering is the more traditional route, used when all the information necessary to calculate a realistic price is available when tendering commences:
- An invitation to tender is issued to prospective suppliers (perhaps following completion of a pre-qualification questionnaire and/or a pre-tender interview). The invitation to tender will include information describing the goods or services required in sufficient detail to enable prospective suppliers to prepare an accurate tender.
- Tenders are prepared and returned by prospective suppliers (this may involve questions and answers and a mid-tender interview to clarify the client’s requirements).
- Submitted tenders are then assessed and compared (this may involve further interviews).
- The preferred tenderer is selected and negotiations opened.
- Subject to the outcome of those negotiations the preferred tenderer may then be appointed.
See Tender for more information.
However, increasingly it is becoming useful to obtain input from prospective tenderers before there is sufficient information available for the main contract to be awarded. This can allow early input from the main contractor, or early appointment of a specialist contractor, such as a cladding contractor, before the main contract has been awarded.
A two-stage tender process may also be adopted on a design and build project where the employer's requirements are not sufficiently well developed for the contractor to be able to calculate a realistic price. In this case, the contractor will tender a fee for designing the building along with a schedule of rates that can be used to establish the construction price for the second-stage tender.
See Two-stage tender for more information.
Two-stage tendering enables the client to transfer design risk to the contractor, but the client inevitably loses leverage as the contractor becomes embedded in the team and competition is less of a threat. However, whilst tender prices for two-stage contracts may initially be higher than single-stage tenders, which are subject to full competition, the final account tends to include fewer variations and fewer claims.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February