Two-stage tender
Contents |
[edit] What is two-stage tendering?
Two stage-tendering is a way of procuring goods or services that involves two-stages of appointment. Traditionally, tendering involves just one stage, in which a tenderer is selected and appointed to carry out all of the works required. In Two-stage tendering, the tenderer is initially appointed only to carry out some of the works required. They are generally then appointed to carry out the rest of the works in a second stage.
[edit] When is two-stage tendering used?
Two stage tendering is often used to allow the early appointment of a contractor (or other supplier), prior to the completion of all the tender information that they would require to be able to offer the client a fixed price - ie the design is still being developed. In the first stage therefore, a limited appointment is agreed allowing the contractor to begin work and in the second stage a fixed price is negotiated for the contract.
It can be used to appoint the main contractor early, but more commonly it is used as a mechanism for early appointment of a specialist contractor such as a cladding contractor in order to access their specialist advice which may be necessary to properly complete the design.
It may also be used on a design and build project where the employer's requirements are not sufficiently well developed for the contractor to be able to calculate a realistic price. In this case, the contractor will tender a fee for designing the building (or completing the design) along with a schedule of rates that can be used to establish the construction price for the second stage tender.
[edit] How are first-stage appointments made?
The first-stage appointment might be made on the basis of a bespoke agreement, a consultancy agreement or a pre-construction services agreement (PCSA), with an appendix setting out all tender items to be applied to the second stage contract, and a clause that makes it clear there is no obligation to proceed to the second stage, and in such circumstances the first stage fee would be full and final settlement of the contractor's costs.
The basis of the appointment for the first stage may include:
- A pre-construction and construction programme.
- Method statements.
- Detailed preliminaries including staff costs.
- Agreed overheads and profit.
- A schedule of rates to be applied to the second-stage tender.
- Agreed fees for design and other pre-construction services.
- CVs for proposed site and head office staff.
- Tendering of any packages that can be broken out and defined.
- Agreed contract conditions to be applied to the second-stage construction contract.
It is important that this appointment is based on as much information as possible and that requirements are well defined, as subsequent changes could prove expensive.
The pre-construction services carried out by the contractor in the first phase might include:
- Helping the consultant team develop the design, or the contractor undertaking all design development themselves.
- Helping the consultant team develop the method of construction, or the contractor developing the method of construction themselves.
- Obtaining prices for work packages from sub-contractors or suppliers on an open book basis.
It is in the client's interests to try to include some packages in the first phase, and to ensure that they have some means of securing an alternative bid if negotiations with the preferred contractor fail, albeit this is likely to result in delays and difficulties regarding design liability. However, the client may find the competition lose interest once they find out that another contractor been awarded the first stage tender.
[edit] How is the second stage appointment made?
Ideally the second-stage negotiation is simply a mathematical exercise using the pricing criteria agreed in the first stage agreement. In reality however, there will be some items not previously considered, around which negotiations will ensue. In the case of sub-contractors, the second stage construction contract is negotiated by the main contractor subject to the approval of the design team.
NB: On a management contract, a single agreement is likely to cover both pre-construction and construction services, with a notice to proceed between the two, before which works contracts cannot be let.
[edit] What are the benefits of two-stage tendering?
Two-stage tendering can allow a project to progress before the design is complete. Early involvement of the contractor (or other supplier) should also improve the buildability and cost-certainty of the design as well as creating a better integrated project team and reducing the likelihood of disputes.
Two-stage tendering enables the client to transfer design risk to the contractor, however the client inevitably loses leverage as the contractor becomes embedded in the team and competition is less of a threat. However, whilst tender prices for two-stage contracts may initially be higher than single-stage tenders, which are subject to full competition, the final account tends to include fewer variations and fewer claims. A longer period of familiarity with the project creates better relationships as well as a reduction in learning curves and programme performance.
[edit] Related articles on Designing Buildings
- Appointing consultants.
- Competitive tender.
- Construction contract.
- Design and build.
- Early contractor involvement.
- Integrated project team.
- Open book accounting.
- Optimised contractor involvement.
- Pre-construction services agreement.
- Preliminaries.
- Procurement route.
- Single-stage tender.
- Specialist contractor.
- Sub contractor.
- Tender.
- Tender processes.
- Two stage open book.
[edit] External references
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
Hi folks,
the definitions of the first stage and the second stage are not the same in this article and the rics article referenced at the bottom.
Can we get some clarity on which is the correct interpretation?
There are different forms of two-stage tendering depending on the nature of the project and what the client is trying to achieve.