Post occupancy evaluation of completed construction works
Contents |
[edit] Introduction
Continual learning and dissemination of acquired knowledge holds the key to shaping the future of projects and practices.
The Home Quality Mark One, Technical Manual SD239, England, Scotland & Wales, published by BRE in 2018, states that: 'Post Occupancy Evaluation (POE) is the umbrella term for the process of obtaining feedback on the performance of a recently completed new building or refurbishment. Over time the value of POE has been recognised not only as a one off evaluation of a recently completed project, but as an ongoing assessment process for any building in use that should be conducted at regular intervals over the building’s life cycle.'
Post occupancy evaluation can be used to evaluate a development to determine:
- How successful its delivery was.
- How successful the completed development is.
- Where there is potential for further improvement
- What lessons can be learned for future projects.
The concept originally surfaced in the 1970s, but the resurgence in POE today is being driven by tighter environmental targets, new regulations and the focus on a more sustainable approach. It is central to improving the performance of low- and zero-carbon building design, and vital for sustainable construction.
The process of post occupancy evaluation can be visualised as part of the building lifecycle, where information learnt from an operational (and occupied) project can be used to inform decisions at all the stages in the design and operational life of a future building.
[Image courtesy Buro Happold]
Post occupancy evaluation can be particularly valuable to repeat developers and may be a requirement of some funding bodies. It may be carried out by a consultant, by independent client advisers, or by an in-house team established by the client. It may also be part of a wider aftercare service such as that outlined by the soft-landings framework.
However, as post occupancy evaluation is likely to take place after the main construction contract has been completed, consultant team appointments may also be completed unless post-occupation services were a specific requirement of the original appointments.
Ideally, the client should commit to carrying out post occupancy evaluation at the beginning of the project so that appointment agreements and briefing documents include requirements to test whether objectives were achieved.
Post occupancy evaluation may comprise two studies:
- A post-project review to evaluate the project delivery process.
- An assessment of performance in use.
[edit] Post project review
A post project review may begin during the defects liability period.
When the development is first occupied by the client, it is important to visit the site immediately to identify any issues that need to be addressed quickly. It can be beneficial to establish a help-desk and rapid response team to resolve issues as they arise.
A post-project review is undertaken to evaluate the effectiveness and efficiency of the project delivery process. To undertake a post-project review, it is important to seek the views of contractors, designers, suppliers and the client about how well the project was managed. This may include assessments of how well the delivery of the project performed against key performance indicators, such as:
- The quality of briefing documents.
- The effectiveness of communications.
- The performance of the project team.
- Quality issues.
- Health and safety issues.
- Certification.
- Variations.
- Claims and disputes.
- Collaborative practices.
An evaluation can then be made of what lessons could be learned from the approach taken and an assessment and lessons-learned report prepared.
See also: End of contract report.
[edit] Performance in use
Generally, performance in use assessments cannot begin until 6 to 12 months after occupation, as operations may not be properly established and the building will not have operated in all seasons. They may then be part of a continuous process.
An assessment of performance in use can include:
[edit] Business objectives
- The achievement of business case objectives.
- Whole-life costs and benefits against those forecast.
- Whether the project continues to comply with the business strategy.
- Whether operations have improved.
- The resilience of the development and business to change.
- Business and user satisfaction (including staff and user retention and motivation).
[edit] Design evaluation
- The effectiveness of the space planning.
- Aesthetic quality.
- The standards of lighting, acoustic environment, ventilation, temperature and humidity.
- Air-pollution and air quality.
- User comfort.
- Maintenance and occupancy costs.
- Defects.
- The balance between capital and running costs.
- An assessment of whether the development is being operated as designed.
- Environmental and energy consumption in use. NB: Regular evaluation of energy consumption is mandatory for certain types of buildings under the Energy Performance of Buildings (Certificates and Inspections) (England and Wales) Regulations). See the article on energy certificates for more information.
[edit] Assessment
The assessment should compare findings to the original targets set out in the business case (the original targets may need to be updated to reflect; changes to the project brief during the design process, inflation etc). It should also compare findings to other projects and industry standards and compare the outcome of the project with the position had the project not taken place.
A report should be prepared that identifies issues, recommends remedies, and makes suggestions for improvements in performance for future projects.
[edit] Other services
Other services that could be provided by consultants during this period might include providing advice on:
- Letting.
- Rating.
- Maintenance.
- Energy consumption.
- Insurance.
- Tenants queries.
- Facilities management.
- The production of energy performance certificates.
- BREEAM assessments.
- Performance of exemplar buildings in use: Bridging the performance gap FB 78.
- The preparation of tender documents for maintenance and operation contracts.
NB The RIBA Plan of Work 2013 defines post-occupancy evaluation as; 'Evaluation undertaken post-occupancy to determine whether the Project Outcomes (both subjective and objective) set out in the Final Project Brief have been achieved.'
See also: Post occupancy evaluation process.
[edit] Related articles on Designing Buildings Wiki
- BREEAM Post occupancy evaluation.
- Building performance evaluation.
- Building performance evaluation in non-domestic buildings guide – an introduction to the tests and methods in non-domestic buildings
- Building performance metrics.
- Building use studies (BUS).
- Closing the gap between design and as-built performance.
- Defects liability period.
- Design quality indicator DQI.
- End of contract report.
- Energy performance certificates.
- Extended aftercare.
- Initial aftercare.
- Maintenance.
- Migration strategy.
- Occupation.
- Performance gap.
- Performance in use (starter article that repeats some of the text in this article).
- Post occupancy evaluation process.
- Post opening project evaluation.
- Post project review (starter article that repeats some of the text in this article).
- Soft landings.
[edit] External references
Featured articles and news
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.
London Build Fire and Security Expo
20-21 Nov and now with new Ambassador Programme..