Method statement for construction
Method statements are widely used in construction as a means of controlling specific health and safety risks that have been identified (perhaps following the preparation of a risk assessment), such as lifting operations, demolition or dismantling, working at height, installing equipment, the use of plant, and so on.
A method statement helps manage the work and ensures that the necessary precautions have been communicated to those involved.
The process of preparing a written method statement provides evidence that:
- Significant health and safety risks have been identified.
- The co-operation of workers has been ensured.
- Safe, co-ordinated systems of work have been put in place.
- Workers have been involved in the process.
Method statements are not a requirement of the Construction (Design and Management) Regulations, however they are identified by the Health and Safety Executive (HSE) as being one way of satisfying the requirements of the regulations and as an effective means of assessing risks, managing risks, collecting workers’ views and briefing workers.
The fact that method statements are not a requirement of the CDM Regulations is evidence of the HSE's intention that implementation of the requirements of the CDM Regulations should not be a paper exercise, where the filling out of a standard template is sufficient, but that it should be an integral and fundamental part of the construction process.
The format in which method statements are prepared, reviewed and used should be set out at the outset of a project, perhaps within the Project Execution Plan (PEP), ensuring not only that the method statement is produced by a competent person, but that it is peer-reviewed as part of the quality assurance (QA) system prior to its use.
Where they are prepared, method statements need be no longer than is necessary for them to be effective. They are for the benefit of those carrying out the work and so should be clear, not over-complicated, and illustrated where necessary.
Method statements should be written by a competent person who is familiar with the process being described and may need to be agreed between the client, principal contractor and contractor. The HSE suggests that those preparing method statements should consider:
- Is there a safer way of doing this task?
- Will workers actually implement the controls as planned?
- Do controls make the job difficult or inconvenient?
- Are there small changes that will improve the intended method?
- How will controls work in adverse conditions?
- Will workers require additional briefing or instructions?
The contents of a method statement will vary with the work process being described, however, it may contain:
- Details of the organisation in control of the activity.
- Details of the individual responsible for the activity.
- A description of the activity.
- A description of how the work will be managed.
- The location of the activity, its boundaries, means of access and how it is segregated from other activities.
- Plant and equipment required.
- The procedure for changing the proposed method of work if necessary.
- A step by step description of the activities to be undertaken.
- Precautions necessary to protect workers, and other people that could be affected, including personal protective equipment and ventilation requirements.
- Training procedures.
- The need for specially-trained operators for certain activities.
- Emergency procedures, including the location of emergency equipment.
- The handling and storage of materials and pollution prevention procedures.
- Temporary works designs.
- The method for safeguarding existing structures.
For more information, see How to write a method statement.
Together, risk assessments and method statements are sometimes described as 'RAMS'. RAMS may be required by third parties to demonstrate that health and safety has been properly considered and that the requirements of the CDM regulations have been satisfied.
For example, a contractor may require submission of RAMS from sub-contractors, a landlord may require submission of RAMS from tenants proposing to carry out works to a property, or a client may require submission of RAMS from contractors operating on their premises.
NB: George Forster in his book 'Construction Site Studies' details method statements used for management purposes showing personnel needed, time, and work output among other factors.
[edit] Related articles on Designing Buildings
- CDM.
- Construction management statement.
- Contractor.
- Deleterious materials.
- Demolition.
- Health and safety.
- How to write a method statement.
- Injuries on construction sites.
- Interface risk in construction.
- Method of procedure.
- Permit to work.
- Personal protective equipment.
- Principal contractor.
- Project execution plan.
- Project risk.
- Reporting accidents and injuries on construction sites.
- Risk assessment.
- Risk assessments and method statements.
- Risk feedback.
- Risk management.
- Temporary works.
- Standard operating procedure.
Featured articles and news
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Heat pumps, vehicle chargers and heating appliances must be sold with smart functionality.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.
Many resources for visitors aswell as new features for members.
Using technology to empower communities
The Community data platform; capturing the DNA of a place and fostering participation, for better design.
Heat pump and wind turbine sound calculations for PDRs
MCS publish updated sound calculation standards for permitted development installations.
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.