Groundworks on construction projects
Contents |
[edit] Introduction
The term ‘groundworks’ refers to work done to prepare sub-surfaces for the start of construction work. Aside from any demolition or site enabling works that may need to be carried out, groundworks are usually the first stage of a construction project and may include:
- Ground investigation.
- Site clearance.
- Substructure and ground stabilisation works.
- Site services.
- Landscaping.
[edit] Ground investigation
As a matter of good practice and a legal requirement of most local authorities, a ground investigation of the site is generally carried out to help identify past land uses, stability and potential problems. These investigations allow data to be accumulated and used for effective design, as well as allowing any potential defects or issues, such as contamination or abandoned mine workings, to be considered.
An assessment of ground conditions typically includes geology, hydrology, hydrogeology, soil conditions and contaminated land issues.
See: Ground conditions for more information.
[edit] Site clearance
As part of the initial preparatory works, the site will generally need to be cleared and the topsoil taken up from the footprint of the structure. The depth will depend on the lay of the land, and if it is a sloping site then the ground may need to be levelled. If required, retaining walls may be constructed in order to create level development platforms.
[edit] Substructure and ground stabilisation
Substructure is defined by the RICS as ‘All work below underside of screed or, where no screed exists, to underside of lowest floor finishes including damp-proof membrane, together with relevant excavations and foundations (includes walls to basements designed as retaining walls).’
Retaining walls can be made from stone, brick or blockwork, reinforced concrete or timber. Basement excavations commonly use sheet piling which is a relatively cheap method of retaining wall construction. This involves the use of a large scale hydraulic jack hammer to drive steel sheet piles into the ground and interlocked, forming a continuous wall.
Other methods of ground stabilisation include:
[edit] Soil nails
Holes drilled and steel bars inserted into the slope face which are then grouted in place. Mesh is attached to the bar ends to hold the slope face in place.
For more information, see Soil nailing.
[edit] Ground anchors
Steel cables with metal wedges on their ends. The metal wedge end is driven pneumatically into the slope face to the desired depth, the cable pulled taut and attached to a finishing plate to maintain tension.
[edit] Geosynthetic materials
These can be incorporated into retaining walls and embankments and provide reinforcement. Geotextiles are woven and allow the passage of ground water through them. Geomembranes are impermeable and are typically used as liner materials. Geocomposites combine both materials.
Foundations provide support for structures, transferring their load to layers of soil or rock that have sufficient bearing capacity and suitable settlement characteristics. There are a very wide range of foundation types suitable for different applications, depending on considerations such as:
- The nature of the load requiring support.
- Ground conditions.
- The presence of water.
- Accessibility.
- Sensitivity to noise and vibration.
Very broadly, foundations can be categorised as shallow foundations or deep foundations. Shallow foundations are typically used where the loads imposed by a structure are low relative to the bearing capacity of the surface soils.
Deep foundations are necessary where the bearing capacity of the surface soils is not adequate to support the loads imposed by a structure and so those loads need to be transferred to deeper layers with higher bearing capacity.
See: Foundations for more information.
[edit] Services
Site services may include temporary and permanent drainage and other utilities connections. Complex sites may require specialist tunnelling or shaft sinking solutions to enable service ducts and cabling to the installed. Existing services such as water and electricity cables may also need to be altered.
[edit] Landscape
Landscaping may include earthworks to remodel the site and hard landscape such as ‘black top’ surfacing of roads and car parks.
See: Landscape design for more information.
[edit] NBS categorisation
NBS categorise groundworks as:
D20 | Excavating and filling |
D21 | Ground gas collection and venting systems |
D30 | Piling |
D40 | Embedded retaining walls |
D41 | Crib walls, gabions and other gravity retaining walls |
D45 | Soil nailing |
D50 | Underpinning |
[edit] Related articles on Designing Buildings Wiki
- Backfilling.
- Building foundations.
- Continuous flight auger piles.
- Diaphragm wall.
- Driven piles.
- Excavation.
- External works.
- Footings.
- Ground conditions.
- Ground heave.
- Ground improvement techniques.
- How deep should foundations be?
- Micropiles.
- Pad foundation.
- Pile foundations.
- Raft foundation.
- Retaining walls.
- Screw pile foundations.
- Settlement.
- Sheet piles.
- Subsidence.
- Substructure.
- Temporary works.
- Trench.
- Trial pit.
- Underpinning.
- Underreaming.
[edit] External references
- Homebuilding - What will it cost getting out of the ground?
- The Construction Centre – Groundwork and substructure
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February