Delay notice
A delay notice is a formal communication issued by a contractor or subcontractor to notify the client (or sometimes the main contractor) of a delay that affects the progress of the construction works. This could be due to various reasons such as unforeseen site conditions, weather, supply chain issues and so on.This notice is a crucial part of project management and contractual compliance, as it informs the relevant parties about disruptions and helps manage expectations, mitigate risks, and assess potential impacts on project timelines and costs.
Many construction contracts, including standard forms like those from JCT (Joint Contracts Tribunal) or NEC (New Engineering Contract), include provisions that require contractors to issue a delay notice within a specified time frame once a delay is identified.
Proper documentation and record-keeping are critical. The delay notice should be well-documented, with all relevant evidence and supporting information to substantiate the claim of delay.
A typical delay notice might include:
- A detailed explanation of the cause and nature of the delay.
- The date the delay began and the estimated duration of the delay.
- Assessment of how the delay will affect the project’s timeline, milestones, and completion date.
- Steps being taken to mitigate the delay.
- Any requests for extensions of time (EOT) or additional resources.
Prompt issuance of a delay notice is essential. Contracts often specify a time limit within which the notice must be given after the contractor becomes aware of the delay. Failure to provide timely notice can affect the contractor's ability to claim an extension of time or additional costs.
The delay notice is typically the first step in the process of applying for an extension of time. If the delay is justified and beyond the contractor’s control, the contract administrator may grant an EOT, thereby adjusting the project schedule without imposing liquidated damages for late completion.
[edit] Related articles on Designing Buildings
- Acceleration.
- Compensation event.
- Concurrent delay.
- Contractor delay.
- Critical path.
- Culpable delay.
- Delay.
- Delay to completion.
- Delay to progress.
- Dispute resolution.
- Disruption claims in construction.
- Employer delay.
- Extension of time.
- International research into the causes of delays on construction projects.
- Liquidated damages.
- Long lead-time item.
- Programme.
- Relevant event.
- Relevant event v relevant matter.
- Relevant matter.
Featured articles and news
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Heritage staff wellbeing at work survey.
A five minute introduction.
50th Golden anniversary ECA Edmundson apprentice award
Showcasing the very best electrotechnical and engineering services for half a century.
Welsh government consults on HRBs and reg changes
Seeking feedback on a new regulatory regime and a broad range of issues.
CIOB Client Guide (2nd edition) March 2025
Free download covering statutory dutyholder roles under the Building Safety Act and much more.
AI and automation in 3D modelling and spatial design
Can almost half of design development tasks be automated?
Minister quizzed, as responsibility transfers to MHCLG and BSR publishes new building control guidance.
UK environmental regulations reform 2025
Amid wider new approaches to ensure regulators and regulation support growth.
The maintenance challenge of tenements.
BSRIA Statutory Compliance Inspection Checklist
BG80/2025 now significantly updated to include requirements related to important changes in legislation.
Shortlist for the 2025 Roofscape Design Awards
Talent and innovation showcase announcement from the trussed rafter industry.
OpenUSD possibilities: Look before you leap
Being ready for the OpenUSD solutions set to transform architecture and design.
Global Asbestos Awareness Week 2025
Highlighting the continuing threat to trades persons.
Retrofit of Buildings, a CIOB Technical Publication
Now available in Arabic and Chinese as well as English.