Cost plus contract
Contents |
[edit] What are cost plus contracts
Cost plus contracts are a form of contract whereby the contractor's costs are reimbursed along with a further payment, the nature of which depends on the form taken. As such these types of contract fall under the general category of cost reimbursable contracts, which might be considered higher risk from the client side because the final cost might not be specifically known or defined, although opinions differ on this point. The use of a guaranteed maximum price (GMP) along side cost plus has been one solution to this.
[edit] Cost plus, cost reimbursable and prime cost contracts
JCT has suggested that cost plus contracts, cost reimbursable contracts and prime cost contracts, are in fact the same, whilst others consider they differ as cost of work packages (the prime cost) are reimbursed, but the main contractor takes on risks of staffing, overhead costs and profit.
[edit] Prices and provisional sums
The disagreement or confusion may lay in the differences between the terminologies of fixed price, firm price, lump sum, stipulated sum, prime cost, guaranteed maximum price (GMP) and so on. The differences essentially being in the considered accuracy of the said amount, and which aspects are covered. For example the inclusion of defined provisional sums, undefined provisional sums, contingencies or allowances within the total might be for items of work that cannot be specifically priced by the contractor and as such may detract from accuracy leading to the use of GMP.
[edit] Types and terms describing cost plus contracts
There are a number of variations, as well as terms, that describe cost plus contracts, which also vary depending on the country of their use, some examples of these are described below.
[edit] Cost plus (Cost +) fixed percentage contract
Cost + Fixed Percentage Contract – Contractor will be entitled to Cost and profit percentage as agreed before.
[edit] Cost plus (Cost +) fixed fee contract
Cost + Fixed Fee Contract – Contractor will be entitled to Cost and Fixed fee as a profit
[edit] Cost plus (Cost +) fixed fee with Guaranteed Maximum Price Contract
Cost + Fixed Fee with Guaranteed Maximum Price Contract – Contractor will be entitled to Cost and Fixed fee as a profit, But the cost of the project should not exceed the agreed amount
[edit] Cost plus (Cost +) award fee contract
Cost + Award Fee contract is essentially the same as Cost + Fixed Fee Contract, allow the contractor to be awarded a fee usually for good performance.
[edit] Cost plus (Cost +) incentive fee contract
Cost + incentive fee contract is essentially a different description of the same as above, it may describe when the contractor is given a fee if their performance meets or exceeds expectations.
[edit] Multiple Incentive Contracts
Multiple Incentive Contracts are another term for incentive contracts that relate normally to the standard three areas of cost, quality and time, but could be expanded or defined in more detail.
[edit] Related articles on Designing Buildings
- Benchmarking.
- Building performance.
- Business plan.
- Contracts for Difference.
- Contingent liabilities.
- Cost plan.
- Cash flow.
- Cost reimbursable contract.
- Contingencies in construction.
- Contingency plan.
- Defined provisional sum.
- Energy performance contracts.
- Estimate.
- Fixed price construction contract.
- Guaranteed maximum price for construction contracts.
- Low Carbon Contracts Company.
- Lump sum contract.
- Milestones.
- Performance.
- Performance contracting.
- Performance incentives in contracts.
- Performance requirements.
- Preliminaries in construction.
- Prime cost contract.
- Project risk.
- Provisional sum.
- Retention.
- Undefined provisional sum.
- Value management.
- Whole life costs.
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.