Preliminaries in construction
Contents |
[edit] What are preliminaries?
Preliminaries (or 'prelims') may form part of tender documents used to obtain bids for construction works or for the supply of goods or materials. Preliminaries provide a description of a project that allows the supplier (often a contractor or subcontrator) to assess costs which, whilst they do not form a part of any of the packages of works required by the contract, are required by the method and circumstances of the works. NBS suggest that 'the purpose of preliminaries is to describe the works as a whole, and to specify general conditions and requirements for their execution, including such things as subcontracting, approvals, testing and completion.' Preliminaries and work sections together describe what is required to complete the works required by the contract.
The costs attached to preliminaries may also be referred to as 'preliminaries' or 'prelims', or as 'site overheads', or general cost items or expenses. The Code of Estimating Practice published by the Chartered Institute of Building (CIOB) describes preliminaries as: '...the cost of administering a project and providing general plant, site staff, facilities, and site based services and other items not included in the rates.'
[edit] What might preliminaries include?
Preliminaries in tender documents might include:
- A general summary.
- Method statements.
- Pre-construction information.
- A description of any planning conditions or other conditions that may affect the works.
- A description of any outstanding statutory approvals that may fall to the supplier to satisfy.
- Party wall requirements or other agreements with, or rights of, neighbours (such as rights to light).
- Any emergency services obligations.
- A description of the reporting information that the supplier will be required to submit (often on a monthly basis) describing construction progress (including a detailed critical path programme, key performance indicators and earned value analysis). See Construction progress reports for more information.
- A description of the commissioning strategy, separating setting to work and balancing tasks from independent verification by the consultant team.
- Relevant reports (such as soil reports).
- An information release schedule.
- Quality management procedures.
- Labour relations.
- Schedules of mock-ups, testing and samples required from the supplier.
- The method of sub-contracting.
- Requirements for insurance, performance bonds, warranties and product guarantees.
- Requirements for the operating and maintenance manual.
- Requirement for progress photos to be taken on site during construction and off-site during fabrication.
- Dates for partial possession.
- Collaborative practices.
- Building information modelling (BIM) requirement and protocols (including requirement for BIM in sub-contracts).
- Site waste management plan.
- Contractor's site preliminaries, such as; staff, welfare provisions, site offices, plant, site waste clearance, water, electricity, furniture, ICT and consumables, rates, protection of work, protective clothing, site transport, setting out, building control fees, and so on.
NB: Preliminaries should not be confused with 'preambles' which set out things such as tendering procedures, that will not affect the contractor's price. For more information, see Difference between preliminaries and preambles.
[edit] Other definitions of preliminaries
According to NRM1: Order of cost estimating and cost planning for capital building work, main contractor’s preliminaries are; '...items which cannot be allocated to a specific element, sub-element or component. Main contractor’s preliminaries include the main contractor’s costs associated with management and staff, site establishment, temporary services, security, safety and environmental protection, control and protection, common user mechanical plant, common user temporary works, the maintenance of site records, completion and post-completion requirements, cleaning, fees and charges, sites services and insurances, bonds, guarantees and warranties. Main contractor’s preliminaries exclude costs associated with subcontractor’s preliminaries, which are to be included in the unit rates applied to building works.'
NRM1 defines ‘subcontractor’s preliminaries’ as; ‘…preliminaries that relate specifically to building work which is to be carried out by a subcontractor. Costs associated with subcontractor’s preliminaries are to be included in the unit rates applied to sub-elements and individual components.’
According to ‘Elemental Standard Form of Cost Analysis, Principles, Instructions, Elements and Definitions, 4th (NRM) Edition’ written by RICS in 2012 and published by BCIS, ‘the cost of preliminaries for the building being analysed should be stated and expressed as a percentage of the contract sum excluding preliminaries, contingencies and, where appropriate, contractor’s design fees.’
[edit] Related articles on Designing Buildings
- Bill of quantities BOQ
- Code of estimating practice
- Contingencies in construction
- Difference between preliminaries and preambles
- Form of tender
- Method statement for construction
- New code of estimating practice
- Overheads
- Preamble in construction contracts
- Pre-construction information
- Prime cost sum
- Profit and overheads on construction projects
- Provisional sum
- Subcontractor’s preliminaries
- Tender documentation for construction projects
- The difference between a prime cost sum and a provisional sum
Featured articles and news
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
All of these “preliminaries” are quantifiable, so why should they be expressed as a percentage of the overall costs? This seems a lazy and sloppy way to calculate them, and not particularly accurate, and a licence to print money for the contractor.
In response to comment above: It's true that prelims are quantifiable after the event (eg. at final account) but the best a Contractor can do when tendering on a fixed price basis is make an appropriate allowance to cover the prelim costs it expects to incur. In doing so, it is left with the risk should it incur greater prelim expense during the execution of the works (save for instances like variations, where those costs arose due to factors outside of the Contractor's control). The approach proposed by the OP above would leave all the risk with the Employer and a Contractor could easily substantiate additional prelim costs if it were so inclined.