Comparison of standard project plans used in the construction industry
[edit] What is a plan of work?
A plan of work is an agreed system for classifying different stages in the lifecycle of projects to define, design, construct, operate and decommission built assets. It is important to be clear about the exact definition of project stages as these can be used to establish gateways were decisions are made about whether to proceed with a project, as well as payment points and contractual milestones.
Unfortunately the construction industry has not settled on a single plan of work, and this is very confusing both within the industry and for those working with the industry, such as clients.
This article began by mapping the project stages set out in the RIBA Plan of Work (2007) v the RIBA Plan of Work (2013) v the Designing Buildings Wiki Project Plans v the OGC gateway review process. It has since expanded and developed as different project plans have been published and updated.
[edit] RIBA plan of work 2007 v 2013 v OGC Gateways
The differences between, and areas of similarity between, the RIBA plan of work 2007 v 2013 v OGC Gateways are set out below. These are compared with the plan of work created for Designing Buildings, which places greater emphasis on the crucial early stages of the project when important decisions are made about its nature and scope and whether it should proceed at all. The RIBA plan of work gives undue (but understandable) emphasis on the design stages, which may be less important to the client.
[edit] 2020 RIBA Plan of Work
In 2020, the RIBA Plan of Work stages were changed to:
- 0 - Strategic definition.
- 1 - Preparation and briefing.
- 2 - Concept design.
- 3 - Spatial coordination.
- 4 - Technical design.
- 5 - Manufacturing and construction.
- 6 - Handover.
- 7 - Use.
[edit] BIM Task Group Digital Plan of Work
The 2014 BIM Task Group Digital Plan of Work was based on:
- 0 Strategy
- 1 Brief
- 2 Concept
- 3 Definition
- 4 Design
- 5 Build and commission
- 6 Handover and close-out
- 7 Operation and end-of-life
[edit] Construction Industry Council scope of services
The 2007 Construction Industry Council (CIC) scope of services adopted:
- Stage 1 (Preparation)
- Stage 2 (Concept)
- Stage 3 (Design Development)
- Stage 4 (Production Information)
- Stage 5 (Manufacture, Installation & Construction Information)
- Stage 6 (Post Practical Completion)
[edit] The Construction Playbook
The 2022 Construction Playbook, published by HM Government, adopted:
- Preparation and planning.
- Publication.
- Selection.
- Evaluation and award.
- Contract implementation.
[edit] ISO 19650-2
ISO 19650-2, publsuhed in 2018 adopted:
- Assessment of need.
- Invitation to tender.
- Tender response.
- Appointment.
- Mobilization.
- Collaborative production of information.
- Information model delivery.
- Project close out.
[edit] Soft Landings Framework
The 2018 Soft Landings Framework adopted:
- Inception and briefing.
- Design.
- Construction.
- Pre-handover.
- Initial aftercare.
- Extended aftercare and post occupancy evaluation.
[edit] Plans of work for infrastructure
The nature of infrastructure projects can be different to projects buildings, and so they have tended to adopt their own plans of work.
[edit] The importance of defining the plan of work
Given the complexity of this situation and the potential for misunderstanding the nature of what is meant by different project stages it is important that appointment documents and contracts set out precisely what is required, and at what level of detail for different stages of a project rather than relying on reference to ambiguous names or process maps.
[edit] Related articles on Designing Buildings
- Stage 1: Business justification.
- Stage 2: Feasibility studies.
- Stage 3: Project brief.
- Stage 4: Concept design.
- Stage 5: Detailed design.
- Stage 6: Production information.
- Stage 7: Tender.
- Stage 8: Mobilisation.
- Stage 9: Construction.
- Stage 10: Occupation and defects liability period.
- Stage 11: Post occupancy evaluation.
- BREEAM and RIBA stages.
- Comparison of BIM work stages.
- Design phase.
- Designing Buildings Wiki project plans.
- Gateway.
- Governance for Railway Investment Projects (GRIP).
- nbs.
- OGC gateway review process.
- Project lifecycle for major road projects.
- RIBA.
- RIBA plan of work.
Featured articles and news
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.
Comments
To make a comment about this article, click 'Add a comment' above.
Separate your comments from any existing comments by inserting a horizontal line.
please, what are the differences between RIBA plan of work and GRIP
Why cant the industry settle on one plan and just stick to it. Constant change is confusing for everyone.